This is only a preview of the August 1990 issue of Silicon Chip. You can view 57 of the 112 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Items relevant to "Digital Sine/Square Wave Generator; Pt.2":
Articles in this series:
Articles in this series:
Articles in this series:
|
The generation of electricity in modern
power stations involves engineering of
massive proportions. The power station is a
world of its own, vastly different in scale
from everything else. The race is on for
greater efficiency and minimum costs.
By BRYAN MAHER
Prior to the early 1950s, Sydney's
power stations were built close to
the load centres. Predominant loads
were the city buildings, electric
trams, trains a nd inner suburban
homes and industries.
The power technology of that
time could not transmit large quantities of electricity over great
distances. Therefore, power stations at Pyrmont, Ultimo and White
Bay were built almost under the
shadow of the Harbour Bridge and
supplied the city using short 6.6kV
and 1 lkV cables .
Bunnerong station extended the
Sydney County Council's capacity,
feeding power to the city and
suburbs via llkV and 33kV mains.
The sites chosen were close to
ample supplies of cooling salt
water: Sydney Harbour and Botany
Bay.
Fuel costs
The drawback of these locations
was that coal had to be carried by
rail over great distances from
mines at Lithgow and the Illawarra
coast [any coal supplies below
Sydney are at great depth - more
than 1000 metres down).
A similar situation appeared in
other Australian cities . Brisbane
had power stations built at the intersection of Ann and George
Streets in 1899, at William Street in
32
SILICO N CHIP
1912 and New Farm in 1938 - all
beside the Brisbane River. Coal was
shipped to them by riverboat from
Ipswich.
In those days, the high cost of
electricity was due to:
(1). expensive transport of coal; and
(2). the low thermal efficiency of
boilers and turbines.
There had to be a more economical way! The answers came in
the development of long distance
high voltage power lines, bigger
and better boiler/turbo-alternator
units, and cheaper and shorter coal
transport.
Today, very high voltage transmission lines can carry vast
amounts of electrical energy far
more cheaply than the raw energy
in the form of coal can be carried
by rail. This statement applies for
distances of up to 1000km.
The cost per kWh [kilowatt-hour)
can be further reduced by using
very large boilers, turbines and
alternators. The resulting strategy
has been to locate large power stations close to the coal mines and to
send the generated electricity by
overhead lines to the cities,
whatever the distance.
If a cooling water supply is also
available, that's an extra bonus. If
not, then a water supply and cooling towers must also be constructed. The thermal efficiency of
these heat/steam/mechanical rotational energy conversions is increased by the use of very high
steam pressures and temperatures
- up to 600°C, which is well above
the melting point of many common
metals [tin, lead, zinc) and approaching that of magnesium or
aluminium!
To be economic, such installations must be on a vast scale. For
minimum cost per generated kWh,
modern power station design
therefore favours having just a few
very large turbo-alternators, with
ratings of between 600MW (600
megawatts) and 1.5GW (1500
megawatts or 1.5 gigawatts) being
common.
Compared to these figures, older
machines seem diminutive. The
Ultimo power station had alternators as small as lOMW, while the
four 50MW generators installed at
Pyrmont in 1952/55 were considered huge in those days.
The first Brisbane power station
in 1899 was rated at 45kW and the
1912 William Street Plant at
2.5MW, while New Farm in 1928
contained units each rated at
l0MW. As Australia grew, newer
and bigger power stations were
provided. And this trend shows no
sign of stopping.
Eraring power station
When it was completed, Eraring
was the largest power station in
Australia, generating 2.64GW
[gigawatts) of electricity which
feeds into the NSW state grid
system. Eraring on its own could
supply 10 cities the size of Newcas-
RIGHT: LOCATED NEAR MUSWELLBROOK in the Upper Hunter Valley of
NSW, Bayswater Power Station generates 2.64GW of electricity from four
660MW turbo-generators. Along with Eraring, it is the biggest power
station in Australia and uses four huge natural-draught cooling towers to
cool recirculated fresh water.
'
'
ERARING WAS THE FIRST power station in Australia to be fully equipped
with 660MW generating units and, like Bayswater, has a capacity of 2.64GW.
This station is situated on the western shore of Lake Macquarie near
Newcastle and draws cooling water from the lake.
tle, and in 1982 was the first station
in NSW to be equipped entirely
with 660MW turbo-alternators.
Following seven years of planning and construction, generation
commenced in March 1982 when
the first turbo-alternator set came
on line. The second and third units
were completed in 1983, with the
fourth placed in operation the
following year.
Eraring is situated on the western shores of Lake Macquarie, a
large body of salt water about 28km
long and up to 10km wide. Open to
the ocean at Swansea, the lake consists of many bays and headlands
and has almost 500km of foreshores. Many of Newcastle's suburbs nestle along the shores of this
pleasant fishing and boating area.
Such a large body of water also
provides an excellent cooling supply for the power station's condensers.
From Bonnell's Bay, water at
84,000 litres/s is drawn via a 5km
long canal to a pumping station. To
34
SILICON CHIP
avoid upsetting the local ecology,
this inlet water passes under Dora
Creek through a 260 metre long
concrete tunnel which is 23 metres
wide and 4.8 metres high.
After being lifted to a high level
storage dam, this salt cooling water
descends through pipes to the
powerhouse, there to be pumped
through the condensers associated
with each turbine. The cooling
water is then returned to Lake
Macquarie via a tunnel and canal
to Myuna Bay.
The immense scale of the cooling
system may be judged by the civil
engineering effort involved. The inlet canal required a 2,000,000
cubic metre excavation which was
then lined with 160,000 tonnes of
concrete. The Dora Creek underpass tunnel itself used 16,000 tonnes of concrete. The total canal
system, inlet and outlet, runs for
nearly 9km.
Local mines
The site chosen on Lake Macquarie, as well as affording ample
cooling water, is situated in the
midst of plentiful coal reserves.
Myuna and Cooranbong collieries
(4.5km and 1.8km distant) are captive mines, specially developed to
supply the station. Eraring's total
coal usage is 6,500,000 tonnes per
year.
Coal is delivered from the mines
to the power station by conveyor
belt. Additional supplies come by
road from the nearby Newstand
(close to Fassifern) and Awaba
mines.
By designing larger furnaces and
providing appropriate forced and
induced draft, power stations can
successfully use cheaper low grade
coal. This policy has for decades
allowed the higher grades of steaming coal to be shipped overseas to
produce export income for Australia.
Low grade coal with an energy
rating 23 . 3MJ/kg (megawattseconds per kg) is supplied to Eraring. Bayswater power station uses
coal with an average rating of
22.4MJ/kg. Some coal is treated to
remove impurities before use in the
power station.
In general, in the Newcastle
region, the low gr9-de coal comes
from shallower mines around Lake
Macquarie and in the Muswellbrook area of the Hunter Valley.
The higher grade export coal is
obtained from very deep pits on the
Cessnock field.
Environmental impact
Despite its enormous size, Eraring station is fairly inconspicuous
on the lakeside, largely because it
has no cooling towers. The four
boiler houses blend with the lake
and surrounds and the two slender
200-metre high emission stacks are
virtually unnoticeable against a
cloudy sky background.
Smoke emissions are tightly controlled. The highly successful fabric
flue filters trap 30,000 tonnes of fly
ash annually. This byproduct is not
wasted but is sold for concrete and
roadmaking additives.
Some key dimensions
Eraring's boiler structures are
each 80 metres tall. Each of the
four turbo-alternators is 50 metres
long and weighs 1342 tonnes. They
THESE HUGE TRANSFORMERS at Eraring Power Station step up the generator
outputs from 23kV to 500kV for transmission to the Kemps Creek Substation.
The overall thermal efficiency from coal input to electrical output is 35.4%.
WALLERAWANG POWER STATION, west of Lithgow, contains two 500MW
turbo-alternators plus two 60MW units (the latter used in mid-winter peak
periods) .. A large cooling tower cools the water from the condensers.
each stand on a reinforced concrete foundation consisting of
24,000 tonnes of concrete and 1000
tonnes of steel. All four stand in the
truly gargantuan turbine hall which
is 418 metres long, 27 metres wide
and 38 metres high.
Approximately 7,400,000 litres of
fresh water per day is supplied by
Newcastle city for boiler make-up
water and sundry purposes.
Each of Eraring's four boilers
generates 590kg/s of superheated
steam at 15,860kPa (2200psi) and
538°C. The alternators, running at
3000rpm, each generate 3-phase
50Hz power at 23kV, 20.71kA, giving 660 megawatts at 0.8 power
factor.
Eraring's thermal efficiency is
quite high, at 37.7% from coal input to alternator output. When the
station load is added, the overall efficiency from coal input to station
electrical output is slightly less at
35.4%.
Tough enough
to take it,
wherever you
take it
Fluke 80 Series multimeters come in a rugged, water
and dust resistant case. They
can handle up to 1000 VAC
(RMS)/DC on any terminal and
have an "input alert"™ warning if test leads are in the current jacks and a non-current
function is selected. They are
shielded
against
electromagnetic interference and are
protected against shock and
vibration.
Each Fluke 80 Series multimeter comes in a rugged pro~
tective holster, with a unique
"Flex-Stand"™, which bends
and holds to any shape, allowing the multimeter to be stood
or hung almost anywhere.
To find out just how tough
a Fluke 80 Series multimeter
can be ... call your local Fluke
distributor today.
FLUKE AND PHILIPS - THE T & M AL LIANCE
ij
PHILIPS
AUGUST 1990
35
The Story of Electrical Energy - ctd
ATMOSPHERIC CONDITIONS are
constantly monitored around the
Hunter Valley power stations and
smoke emissions are tightly
controlled.
Bayswater power station
The success of Eraring, together
with the State's increasing demand
for electrical energy, lead to the
building of an almost identical station at Bayswater in the Upper
Hunter River Valley. This was completed in 1986. Bayswater and
Eraring now form the backbone of
NSW's baseload energy supply and
they are presently the two largest
power stations in Australia.
Coal from dedicated open cut
mines at Ravensworth and Swamp
Creek is carried by 13km long conveyor belt systems to the power station. Load cells built into certain
belt support rollers weigh the coal
on-the-run.
Deep underground mines at Liddell and Muswellbrook together
with open-cut mines at BP Howick,
Bayswater-2 and Drayton supply
coal by rail and road.
Liddell power station
Close to Bayswaster is the older
Liddell power station. Built in
1971/73, this installation consists of
four machines, each rated at
500MW.
36
SILICON CHIP
Cooling towers and two fresh
water lakes, Lake Plashett and
Lake Liddell, provide fresh water
coolant for the Liddell and
Bayswater stations. Water comes
from the Glenbourn dam which is
kept filled by 20 gigalitres/year of
fresh water pumped from the Barnard River. This water flows via a
pipeline and pumping system over
the Mt. Royal range into the Hunter
River headwaters above Glenbourn
Dam, supplementing the upper
Hunter's catchment.
Both Liddell and Bayswater are
fed by conveyor belt from the same,
six open-cut coal mines. These are
the only NSW power stations
receiving coal from open cut
operations.
The complex conveyor system
allows coal to be sent from the
mines to the stockpiles at either station. Coal transfer between stations
by conveyor is also possible should
the need arise. Dirt and impurities
are washed out of the coal by
washeries before the coal is crushed to the powder required by the
station's furnaces.
Liddell consumes 2,900,000 ton-
nes of coal plus 13,200 tonnes of
fuel oil annually.
Before Eraring and Bayswater
were operational, Liddell power
station was the largest in the state,
the backbone of the NSW Electricity Commission's generating system.
Now it is third in size. Liddell's
overall thermal efficiency is 29.1 % .
Other lakeside stations
Other large stations in the NSW
system include Vales Point-B on
Lake Macquarie where two
660MW units were installed in
1978/79. Also Munmorah, built in
1967/69 between Lake Munmorah
and Lake Budgewoi, features four
turbo-generators rated at 300MW
each. The older W angi power station is now in dry storage.
Wallerawang
Wallerawang, west of Lithgow
and about 160km from Sydney, is
located on the western coalfields.
The station consists of three parts.
The older A section is now in dry
storage as its small 30MW
machines are less efficient than the
newer additions.
The B station has two 60MW
units. These are classed as intermediate load plant and used only
in mi_d -winter peak periods.
The C station, with two 500MW
turbo-alternators, was commissioned in 1980. The combined 1
gigawatt output of these machines
is an essential component in the
state's base load capability.
Each 500MW turbo-alternator
unit is 48 metres long and weighs
1300 tonnes. This is only fractionally smaller than the 660MW
monsters at Eraring and Bayswater.
Base load and peak load
The six stations we have discussed so far - Eraring, Bayswater,
Liddell, Munmorah, Vales Pt and
Wallerawang-C are together
capable of continuously generating
10.5 gigawatts as long as required.
Normal system practice is to
have the most economic stations,
Bayswater and Eraring, supply the
bulk of the continuous load. As
domestic, industrial and traction
electricity demands vary throughout each day, the other large power
stations in the system take up the
extra load.
By base load we mean the normal
electricity demand over a long
period, neglecting the twice-daily
peaks. Every morning and evening
the state uses more electricity as
people take showers and prepare
meals. This adds considerably to
the base load. The minimum power
demand typically occurs at around
4am every morning.
Included with this article is a
On the alert,
accurate
and safe
Fluke 80 Series multimeters come with a large number
of "alert" functions designed
to ensure safe, easy use.
The "Input Alert" prevents
accidental damage through
wrong lead connection. An
automatic power cut-off (after
30 minutes idle) extends battery life. This may be overridden in 36 hour record mode .
And the readouts couldn't
be easier. Fluke's patented
"Touch Hold" ™ feature, when
activated, captures, locks and
displays each measurement,
yet leaves you both hands free
to position the probes. In the
relative mode, measurements
can be made relative to your
own reference point Arid
there's a maximum/minimum
alert, plus automatic storage
of max/min readings.
And there's much more .
Why not be alert to all the special features of Fluke 80 Series
multimeters . .. call your local
Fluke distributor today.
FLUKE AND PHILIPS - THE T & M ALLIANCE
MYUNA COLLIERY IS ONE of two specially developed underground mines
supplying Eraring Power Station (background). The colliery is 4.5km from
Eraring and delivers its output to the station by conveyor. Eraring's total coal
usage is 6,500,000 tonnes per year.
PHILIPS
A UG UST 1990
37
Eraring was supplying exactly
100% of its rated capacity, while
Bayswater was at 76%.
Notice too that the sharp peaks of
1.3GW around 9am and 6pm were
supplied by the Snowy Mountains
hydroelectric system, where generators can be started and stopped
at short notice. [But that's a story
for another chapter).
Big British ,b oilers
Before closing this chapter, we
should have a look at a modern
overseas power station, to see how
it compares with big Australian
power plants. A good example is
England's Littlebrook-D power station. Situated on the south bank of
the Thames River, this installation
features three 660MW oil fired
boilers and turbo-alternators. It
was built in 1981-2 by NEI (Northern Engineering Industries) Ltd of .
Newcastle and the Central Electricity Generating Board (CEGB) of
England, and it contributes almost
2GW to the British national grid.
Steam at 16,560kPa pressure and
541 °C is generated by boilers
which are oil-fired rather than using coal. The boilers are every bit
as big as Australian units, containing thousands of tubes made from
carbon-chromium-molybdenum
steel. These tubes, totalling 480km
in length, weigh a total of 6000 tonnes, two-thirds of which hangs
suspended from a steel framework
extending up to 68 metres high.
THE STEAM DRUM for one of the 660MW boilers at Littlebrook Power
Station, Englan_d, during construction. The drum is 35 metres long, 2.5 metres
in diameter and weighs 250 tonnes.
chart showing the winter load used
by the whole state of NSW on a particular day (26th June, 1989). Notice
the big peak in the morning as
people are waking, heating themselves, cooking breakfast and
travelling by electric train between
6am and 9am. By that time, industrial and business loads form a
steady demand until around 4pm on
weekdays.
BELOW: THIS CHART shows the total
load for NSW on the 26th June, 1989,
together with the contribution of each
station. Notice the evening and
morning peaks and the contribution
of the Snowy Mountains hydroelectric
stations.
Then as evening slides into night,
the traction, cooking and heating
requirements reach an all-day high,
until around 11pm when the
general populace tires of TV and
goes to bed.
Observe the evening peak of
8.943GW - a staggering quantity
of electrical power. It is equivalent
to the power drawn by almost 9
million lkW single bar radiators.
The load chart also shows the
contribution of each power station
to that particular day's demand. Of
this , Bayswater generated 2
gigwatts, Eraring 2.65 gigawatts,
Vales Point 1 gigawatt, and
Wallerawang and Munmorah
800MW each. That means that
10000
8943 MW'
System load
B
E.C Pumps
E3
Snowy
[j
9000
8000
7000
SboalhaJ•en
6000
Other
5000
4000
3000
2000
.1000
0200
38
SILICON CHIP
0400
0600
0800
1000
1200
1400
1600
1800
2000
2200
2400
■
111,
THIS VIEW SHOWS one of the boilers at Littlebrook Power Station (England)
during construction. Note the size of the steel girders needed to support the
steam drum and the 6000 tonnes of economiser and reheater tubes. The
station now contributes 2GW to the British national grid.
All the tubes are joined to the
steam drum above. Construction involved 70,000 pressure-tight welds
of which 10,000 were made on site.
Some of the photos in this article
show the boiler in various stages of
construction.
Pre-heating and post-heating was
a necessary part of each welding
operation. Rigorous quality control,
testing and inspection of all welds
is necessary for reliability. 100%
individual ultrasonic and magnetic
particle analysis was used to con. firm that · every weld met the
rigorous specifications necessary
for long life reliability.
During heating from cold to full
temperature, the vertical hanging
tubes extend their lengths by
225mm due to thermal and
pressure expansion. That's a lot of
expansion to cope with while still
maintaining those extreme steam
pressures.
Also part of the suspended mass
in the boilers are the main steam
drums, fabricated from 125mm
thick DucoL-W30 carbon manganese steel. Each drum is 35 metres
long and 2.5 metres in diameter,
and weighs 250 tonnes. Our photo,
taken during construction of the
boiler, shows the massive proportions and the hanging braces carry-
ing the weight of the tubes.
Upon completion, the drum,
steam tubes and pipes were
hydraulically pressure tested, with
only 8 leaks being found in the
140,000 welds of two boilers - an
excellent result!
Each boiler at full load consumes
140 tonnes per hour of heavy
residual oil fuel which is delivered
by ocean going tankers. Oil firing
allows quicker start-up compared
with the use of coal.
In · other respects, England's
Littlebrook-D power station is quite
similar to large Australian stations.
It too does not need cooling towers,
as it is sited right on the river.
Acknowledgements
Grateful thanks and acknowledgement to ASEA and ABB journals, Electricity Commission of
NSW, C. A. Parsons & Co Ltd, Dr
Habibulah, Electronics and Power
Journal, IEEE, IEE, and NEI
Newcastle-Upon-Tyne, for photos,
data and permission to publish.
Finally, the Electricity Commission of NSW advises that inspection
parties are taken on conducted
tours of certain power stations. Interested readers should ring the
Commission on (049) 73 2933 or (02)
268 6800.
~
Count on them
to measure up
1n more ways
■
Fluke
multimeters are
made in the USA, to the highest standards, offering accuracy you can depend on .. . and
they are guaranteed for 3
years by Philips, the name you
can trust
Each
measurement
is
clearly shown on the display,
so you know exactly what
you're measuring .. . without
having to check connections
or switch positions. Fluke
Models 83 and 85 have bar
graphs for analogue readings,
while the Model 87 has a high
resolution pointer.
The 10-times zoom facility
lets you enhance resolution.
And your Fluke Multimeter
comes comp lete with protective holster, safety leads,
9V battery and operating
instructions .
To find out why no other
multimeter measures up . to
the Fluke 80 Series ... ca ll your
local Fluke distributor today.
FLUKE AND PHILIPS - THE T & M ALLIANCE
[e)
PHILIPS
AUGUST 1990
39
|