This is only a preview of the February 1991 issue of Silicon Chip. You can view 47 of the 104 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
|
The Story of
Electrical Energy, Pt.8
The largest hydroelectric machines in
Tasmania are in the Gordon River
underground power station, in the rugged
south western region. The subject of much
controversy in the past, it is an impressive
project by any standard.
By BRYAN MAHER
Exposed to the never-ending moist
gales of the roaring forties , the southwest corner of Tasmania boasts Australia's wettest temp erate climate ,
with 200 rainy days each year. Flora
and fauna, direct relics of ancient
times , still thrive in the cold rainforests . Rugged parallel mountain
.5es lying in a north west to south
easterly direction and broad valleys
cut by inaccessible gorges posed a
nearly impossible task for the surveyors and engineers.
Although recognised since World
War 1, the hydroelectric potential of
the Gordon River was not thoroughly
investigated until 1961. In March of
that year, a hydrology analysis station was established on the Serpentine River. Measurements of precipitation and runoff predicted that 500
to 1000MW could be generated from
the Gordon, Huon and Serpentine
rivers.
That was easier said than done! Just
reaching the site, let alone bringing
in heavy machinery, was a major effort. A rough access track, suitable
only for tracked vehicles , was constructed in 1960 to McPartlan Pass.
Helicopters were necessary to build
research stations on Lake Pedder and
the upper Huon River. The region was
accessible only in summer, when
snowfalls and driving south westerly
gales usually abated.
To verify the choice of dam site on
the Gordon (1.5km upstream from the
Serpentine confluence), a camp was
·established. Here intensive surveying,
geological mapping, exploratory tunnelling and drilling occupied the
summers of 1963 and following years.
Approval by parliament in 1967 of
the $185 million scheme started construction destined to increase the
state's electricity supply by 23 %. The
ambitious plan involved a 140-metre
high dam blocking the precipitous
gorge on the Gordon river. The 260
square kilometres of Lake Gordon thus
formed would join an elevated version of the existing Lake Pedder to
create Australia's largest fresh water
storage. After a road was built to the
dam site in 1969, diversion tunnels
were the next to be built.
River diversion
Taken when the Gordon Dam was almost complete, this photo shows the
extreme curvature of the structure - a classic concrete arch dam.
92
SILICON CHIP
To enable the building of the Gordon Dam, the river had to be temporarily diverted. This was done in two
stages in 1969/70. First, a reinforced
concrete coffer dam was built upstream from the main dam site. The
water thus impounded flowed
through a 350 metre long tunnel bored
through the gorge cliff, exiting well
down stream. Then a second stage
diversion was built closer to the dam.
Subsequently, the first diversion tunnel was sealed with a concrete plug
and the coffer dam demolished in
--:-·-~·
<t~' )'t j,
·~
!i
""'
Most dam projects require at least two dams, one a temporary coffer dam which
lets construction start on the main dam. This upstream photo of the Gordon
Dam during construction shows the remains of the coffer dam after it had been
demolished.
FEBRUARY1991
93
The arched design transfers most
of the water force onto the steep rock
cliffs which form abutments on each
side. Begun in 1972, the dam was
completed in 1974, but it took 4 years
to fill. The weight of water exerts a
pressure of 1.4 megapascals (ie, 14
kilograms per square centimetre) at
the base of the dam wall. As the dam's
security depends on the stability of
the abutments, electronic transducers were buried within the concrete
wall. Computers in Hobart monitor
the electrical readings to constantly
assess the conditions.
At the same time as the dam was
being constructed, an 80-metre high
intake tower was built with an access
bridge above spillway water level. At
the top of the tower are controls for
the 75-tonne cylinder gate valves,
located at the bottom, which control
the bulk water flow to the power station below. The flow of water (415
cubic metres/sec) can be totally
stopped, if need be, by the cylinder
valves in only 20 seconds.
Water falls via the 8.23m diameter
shaft, then runs horizontally to the
turbines, as the cross section diagrams
show. The 356-metre power tunnel
was completed in 1973 and the following year the dam began to fill.
Underground turbine room
This photo shows the underground Gordon power station during construction.
The inlet valve and turbine casing for the No.2 machine can be clearly seen.
1970. Similarly, the Serpentine River
was diverted so its dam could be
commenced.
As the region was totally uninhabited, Strathgordon Village was built
to house the workforce, while design
of a twin 220kV power line to the east
commenced.
The proposed site of the underground power station proved to be
unsuitable because of unfavourable
rock structure. The geology of south
west Tasmania consists of 700 million-year-old sandstone with limestone outcrops and ancient lava intrusions up to 300 metres thick.
A quarry and cement plant was
built on a knob hill overlooking the
river and roads were built to the bottom of the 400-metre deep gorge.
Roads and an overhead cable way
94
SILICON CHIP
carried men and equipment to the
dam site. Using twin haulageways and
four tower cranes, by 1972 the first
concrete was being poured in the
Gordon Dam structure. The following
year, the excavation of the re-sited
underground power station began.
The Gordon Dam
Rising 140 metres above its foundations (higher than Sydney Harbour
Bridge), the Gordon dam is a classic
reinforced concrete arch; the largest
of its kind in the southern hemisphere. Only 200 metres long, it tapers in thickness from 17.68 metres
at the base to 2.74 metres at the top.
Containing 280,000 tonnes of steel
and concrete, the dam is constructed
with its convex curvature facing upstream.
The construction of a power station within the bowels of a mountain
tests the expertise and experience of
engineers to the limit. The procedure
used was to excavate the underground
turbine room from the top downwards. The artificial cave was first
dug out down to crane rail level. The
crane runway structures were set into
the rock walls, then the cranes assembled and operated.
The work then consisted of digging
out the floor using tracked hydraulic
boring equipment until the full 32metre depth was reached.
As machinery was set in place, tiling contractors then lined the ceiling.
The walls were faced and lighting
was set in place. Various floor levels
were then constructed; above and
below the alternators, at basement and
above the turbine runner height.
Reinforced concrete busbar troughs
were built around the walls to house
the generator output conductors
which run from each machine to the
vertical shaft, thence up to the aboveground substation. The final appear-
tured in Germany by Siemens and
assembled on site. The heaviest component is the 269-tonne rotor; so
heavy that it was lifted into place in
sections by the two overhead travelling cranes. The 22-pole stators for
each machine , weighing 168 tonnes
when assembled, were lifted into
position by both cranes.
When fully assembled, the total
314-tonne weight of the rotor, turbine
and coupling shaft hangs on one vertical thrust bearing and is aligned by
a number of guide bearings. So accurate is the alignment and so smooth
the lubricated bearings that two men
can turn the total rotating mass by
hand (at a very slow speed of course).
Having done its work in turning
the turbine, the water falls through
the fabricated steel outlet draft tube
to the tailrace tunnel. This huge conduit , 9 metres in diameter, carries the
Hydroelectric alternators are very big machines, especially compared to those
driven by steam turbines. This is one of the stators in the Gordon Power Station.
ance of the main floor of the power
station, high above the lop of the alternators, is shown in one of the photos. Only the exciters are visible from
the operating floor; stairways give
access down to all other levels.
Simultaneously with the turbine
room construction, the boring of the
inlet and outlet water tunnels proceeded. As already noted, the inlet
shaft has a diameter of 8.23 metres.
This main water conduit and the branchings to each turbine are lined with
concrete and a great deal of trouble
was involved in obtaining smooth
contours throughout.
Smooth contours
Smooth pipe contours are necessary to obtain laminar water flow with
minimum turbulence. Turbulent flow
implies a severe energy loss which
must be avoided for best efficiency
and least wear in the tunnels and
turbines.
The cross section diagram of the
power station shows the water pathway. Controlling the flow through
each turbine is a 2.8-metre diameter
hydraulically operated rotary inlet
valve. The station's two 90-tonne
capacity cranes were used in tandem
to lift these 116-tonne valves into
place during construction. From each
valve, the water flows into the tur-
MAX . LA~f LE VEL
$ .L. 30 &m
bine at a rate of 86 cubic metres per
second.
Francis turbines
Each 150MW Francis vertical shaft
water turbine consists of a welded
steel spiral casing in which the turbine runner rotates. The 100-tonne
spiral casings were fabricated in the
HEC workshops and were then lifted
into position and embedded in concrete. In op eration, the water enters
the spiral casing at the large diameter
end. Flowing around the spiral towards the small diameter end, th e
water is forced to flow through the
turbine runner before falling downwards. The water thus rotates the turbine and the direct coupled alternator above.
Each 3-metre diameter turbine runner, the most critical mechanical
component, was cast by Fuji in one
piece of stainless steel. These 23tonne castings must have smooth
blades polished almost to mirror finish to reduce water friction and enhance efficiency. The chromium
component in the stainless steel alloy
inhibits pitting and corrosion which
would otherwise increase losses.
Each turbine runner is coupl ed by
a long 22-tonne vertical shaft to the
rotor of the alternator above. These
144MW generators were manufac-
LAKE
GORDON
GAU. EI-H•' .... -•··
~---,J~
GHOUl
,/ /.,,j
COfHAIN
t
-. .,. ·-!--··· ORAINAG E
I CURTAINS
l
The cross section of the Gordon Dam
shows it to be a very thin structure,
relative to its height. Note that it is
curved vertically and horizontally.
FEBRUARY1991
95
This photo really does show the scale of the Gordon hydroelectric scheme. This
is the 8.23-metre diameter inlet water tunnel with the three raceways running
off lo Lhe left. Note how smooth the concrete is, to minimise turbulence.
total outlet water from all machines
1.6km downstream to the lower Gordon River.
Scale working model
To test the performance of the turbines and verify the design , the Fuji
Electric Co of Japan constructed a true
118th scale working model. This
model turbine used water flow and
full load to ascertain the efficiency,
speed characteristics , stresses, strains
and the extent of cavitation.
In any turbine of the Francis or
Kaplan types (as with ships' propellers), water flow patterns are critical.
Cavitation means a non-ideal action
wherein the turbine or propeller generates bubbles of water vapour close
to the steel blades. As this water vapour is compressable (whereas liquid
water is not), less than ideal forces
act between turbine blade and bulk
96
SILICON CHIP
water. The result is that full power
transfer cannot be realised from the
machine.
Thermodynamic theory shows that
there will always be some cavitation.
However, this effect can be minimised
by optimum design of blade dimension, shape and contour.
In operation, the generator runs at
272.7272 RPM (long term average). But
as with all generators, the sudden
application of a heavy load must
cause a momentary reduction in speed
until the water valve opens incrementally to compensate. Load reduction
causes the reverse. However, the very
heavy rotating mass of large hydroelectric generators provides a great
spinning reserve of energy, helping to
maintain system frequency during
changes in load.
The 18kV 5000A 3-phase output of
the alternators is carried by hollow
square aluminium busbars through a
190-metre vertical lift shaft to the
aboveground substation. Here the
power is stepped up to 220kV for
transmission to Hobart. Each transformer weighs 194 tonnes, so heavy
that a special technique was used to
transport them to the site.
Carrying frames
Instead of an enormous trailer being
used (which would be too long for
manoeuvrability) a special pair of
carrying frames were built. Each
160MVA transformer was supplied by
the manufacturer, Reyrolle-ParsonsWilson, complete with special transporting frames . After being lifted from
ship to wharf, the triangular frames
were bolted to the front and rear of
the transformer casing. Multiple road
wheels supported each triangular
frame, while a heavy Pacific prime
mover hauled the assembly.
The switchyard and power line in
the Gordon regions were designed to
_________
23 · 165 METRES
,ii!
___,
UHF HIGH GAIN ANTENNAS
!I
if
ii
H
f/
ROCK BOLTS
antenn
existing
systems
triangul
powder
coated
receiving
elements ensures excellent UHF reception
compared to other UHF antennas of similar size
and price. Two models are available: the TVA 14
for Band Four and the TVA 15 for Band Five UHF
reception. Both models are supplied with back
reflectors to prevent ghosting as well as a
waterproof entry box designed to accept 75 ohm
coaxial cable without the need for addittional
baluns. They also have predrilled holes for
securing the tilt adjustable metal mounting
bracket in either a horizontal or vertical position.
90 .i 10 T ON TWIN
OVERH EAD C:__l'! A"'_~S
~········-·····
, __;r~J?~s12y·
l,ll
IIJ
...cc
w
:lF
0
(jt
0
Imported and dlatrfbuted by:
M
ARIS'&
ELECTRONICS
Aval/able through the following retallera:
Ritronlcs.
56 Renver Rd.
Clayton.
V/ctoria. 3168.
(03) 543 2166.
Bernys.
Brldgepoint.
Military Road.
Mosman. 2088.
NSW. (02) 969 1966.
DRAFT TUBE
··-
GATE
CHRISTIAN
BLIND
MISSIQ~ ·d
Re$toti~t t~~~,, M,~
This cross sectional diagram of the Gordon Power Station shows the scale of the
project. The station capacity is 432MW, with provision for two more machines.
blend as much as possible with the
scenic surroundings. ACSR (Aluminium Conductor Steel Reinforced)
conductors 25mm in diameter were
used for the twin power feeders, using an average span length of 450
metres. In the sensitive Gordon River
regions, towers were constructed of a
special steel. This develops a uniform stable rust coating which inhibits further corrosion. The dark colour
blends successfully with natural surroundings.
The first two generators were completed and commenced supplying
load in 1978. Full load commercial
operation was achieved in 1978/79.
After 3½ years work and an expen-
diture of $38 million, the installation
of the third turbogenerator at Gordon
Power Station was completed in 1988.
This raised the total station capacity
to 432MW.
The station still has provision for
two more machines. If installed, these
would raise the available peak load
output. However, the total output in a
year would not be increased as this is
limited by the rainfall and snowfall
within the catchment area.
Lake Pedder
To supplement the water storage of
Lake Gordon, the level of Lake Pedder was raised by the Serpentine and
Scotts Peak dams and the small Edgar
COUPON
Please cut and send to:
CHRISTIAN BLIND MISSION
INTERNATIONAL, P.O . .Box 5,
1245 Burke Road, KEW. Vic. 3101
Phone: (03)817-4566
e
D Please send me further information
about CBMl's work.
As long as it is possible for me, I will help:
monthly D quarterly D annually
D to prevent blindness
D to restore eyesight
D to rehabilitate the blind
Enclosed is my gilt of S _ _ _ _ _ __
D
Mr/ Mrs, Miss,
Street , __ . .
City , _ _ .. .
. P051code,
FEBRUARY1991
97
The third machine, installed in the Gordon Power Station in 1988, raised the
station's maximum output to 432 megawatts.
levee. Though much smaller than the
Gordon, these two additional dams
are an integral part of the scheme.
The Serpentine Dam, on the river
of the same name near Mt Sprent, is a
38-metre high mass of concrete-faced
rockfill 131 metres long. Much bigger
is the Scotts Peak Dam, just over a
kilometre in length but only 43 metres
high and containing about a million
tonnes of rockfill under its concrete
skin. These two small dams, with the
Edgar levee, impound the Lake Pedder catchment, raising the water to
approximately the same level as Lake
Gordon.
The McPartlan Pass Canal, 2.66km
long, was cut to allow water to flow
either way between the two lakes.
Normally water flows from Pedder to
Gordon but flood rains in the Gordon
catchment can also be stored in Lake
Pedder.
The Tasmanian parliament and the
Hydro Electric Commission recognised that the intrusion of man into
previous! y inaccessible wilderness
regions must cause adverse effects.
Certainly the flooding of the small
but beautiful original Lake Pedder
provoked serious environmental controversy.
The Gordon power station contributes a large percentage of the total
state power loading which reached
an all-time peak of 1.4505 Gigawatts
in June 1989.
The control of the entire Tasmanian
hydroelectric system requires many
factors to be taken into account. Not
only must power be immediately
available at all times but also water
resources must be carefully husbanded. Accurate weather forecasts
must be taken into account. These
factors and other Tasmanian dams and
power stations will be investigated in
a later chapter of this series.
References
(1). Tasmanian HEC literature.
(2). "Australia the Beautiful Wilderness"; Bob Brown.
(3). "Australia's Wilderness Heritage"
Vol.1; Geoff Mosley.
(4) . "Australia the Greatest Island";
Robert Raymond.
Acknowledgements
Big alternators require big transformers and these cause big headaches in
transportation. This photo shows the solution used for the Gordon power
station transformers - a special carrying frame hauled by a heavy prime mover.
98
SILICON CHIP
Grateful thanks to the Tasmanian
Hydroelectric Commission and to Liz
Emson for data, photos and permission to publish.
SC
|