This is only a preview of the September 1991 issue of Silicon Chip. You can view 44 of the 96 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Articles in this series:
Articles in this series:
Articles in this series:
|
The Story
Electrical
I
Left: ever wondered how big the
insulators on 330kV lines are?
This photo, taken during the
construction of the 330kV line
from the Murray 1 power station,
gives the answer.
Most power stations in the Snowy
Mountains scheme are underground but
the two largest are above ground, at
Tumut 3 & Murray 1. Tumut 3 is also
used during off-peak times for pumping
water for energy storage.
Leaving behind the Snowy uplands
and Cabramurra (Australia's highest
town), the discharge water from the
underground power stations plunges
downhill to fill Talbingo reservoir
w~ich is 544 metres above sea level.
Lying in the steep gorges of the upper
Tumut river valley, the waters are impounded by Talbingo Dam, the most
88
SILICON CHIP
massive structure in the Snowy system.
Talbingo Dam is 162 metres high
and over 600 metres thick at its base,
and contains over 20 million tonnes
of earth and rockfill. Its capacity is
921 gigalitres. The function of this
reservoir is to provide the water head
for Tumut 3 power station, the largest
by far in the Snowy scheme.
From the darn, water flows via a
945-rnetre long headrace channel to
the pressure pipeline inlet structure.
This channel, 92 metres deep and up
to 190 metres wide, took three years
to complete. The headrace channel
feeds water into the six pressure pipelines which feed the power station.
Each pipeline, 5.56 metres in diameter, is big enough to drive a doubledecker bus through. The pipes were
constructed of rolled medium-tensile
steel plate up to 30.2mm thick, manufactured in sections and joined by
electric welding on-site.
Each pipe has to withstand enormous forces in service - the pressure
of the 150.9-rnetre head and the inevitable turbulence from the water flowing at up to 189 cubic metres per
second. Therefore, the welding of pipe
sections was a critically controlled
operation.
For stress-free welds, the pipes were
heated to 66°C and held at that temperature, while electric welding was
performed. Imagine, if you will, a
tradesman arc welding inside that hot
pipe section! But it had to be done at
every joint in more than 10,000 tonnes
By BRYAN MAHER
of
Energy, Pt.13
of steel pipe. N0 1 wonder the construction of the six pipelines took 4½
years!
Tumut 3 power station
Largest by far in the Snowy scheme,
the above-ground Tumut 3 power station generates up to 1500 megawatts.
The six 250MW alternators were the
largest water-driven machines in Australia at the time of installation (between 1968 and 1972). Of the vertical
shaft salient-pole type, each rotates
ever so quietly at only 187.5 RPM.
They have 32 poles and produce
15.4kV which is transformed up to
346kV for statewide transmission.
The huge machine hall is 154 metres long and 60 metres high. The
alternators are on original ground
level, with the Francis type water turbine equipment extending 33 metres
below.
Two 130/20 tonne capacity overhead travelling cranes, used to construct the machines, are now used
only for maintenance operations. For
heavy lifts such as on the enormous
generator rotors, both 130-tonne hoists
are used in tandem using a special
lifting beam.
Unlike all the other power stations
in the Snowy, the tailwater from the
Tumut 3 water turbines flows uphill
against a small head - 16.5 metres
maximum. This water forms Jounama
pondage, captured by the small
Jounama Dam, a rockfill/ earthfill wall
44 metres high, 5.8km downstream
from the power station.
Pumped storage
The eternal problem in all electricity generating systems is the daily
cycle of peak and off-peak loads. Demand in NSW may be as high as 9
gigawatts during winter evening peaks
but may fall to as low as 4.4 gigawatts
around 4-5am the next morning:
Steam-driven generating plants,
with their slow thermal stabilisation
time, cannot cope with such large variations. Start-up time is usually many,
ma:µy hours and it is very difficult
and inefficient to have boilers up to
temperature, ready for load, but not
yet needed. Large modern boilers have
a minimum load value and cannot be
operated at lower demand.
Ideally, the thermal power stations
should be used for supplying the constant base load 24 hours per day. The
Snowy power stations can then be
used at their full capacity only during
the large morning and evening peaks.
They can be brought on line very
quickly, within a few minutes, and
then taken off line just as quickly.
Water turbines are large machines as this photo of a turbine spiral casing
shows. Ten of these 97MW machines are installed in the Murray 1 power
station. Water flows through each turbine at a rate of 241 cubic metres/second.
SEPTEMBER1991
89
Tumut 3 power station is notable not only because it is the biggest power station
in the Snowy scheme but because it also pumps water back up into Talbingo
reservoir for use at peak times. It uses six 250MW alternators.
Obviously, in dry times, there may
be a limit to the amount of water
available. We don't want to empty the
dams just to supply peak hour electricity demands. To get around that
problem, the Snowy scheme uses
pump storage.
To this end, three of the six machines at Tumut 3 power station are
provided with extra equipment. As
the cross section diagram shows, the
three units at the western end of the
station have much longer vertical
shafts.
In generating mode, the alternator
is driven by the 254MW water turbine
immediately below it. Further below
90
SILICON CHIP
this , at the bottom of the shaft, is a
huge centrifugal pump capable of
pumping 100 cubic metres of water
per second uphill against a 155-metre
head.
In pumping mode, the alternator is
operated as a 250MW synchronous
motor, driven by electrical power
drawn from the state grid. This is
done only during early morning,
around 1-4am. In this mode the machine rotates in the same direction
and at the same speed as it does when
generating.
Force pumping
Lift pumping with the pump above
water is unsatisfactory and severely
limited due to cavitation (ie, water
vaporising around the pump blades).
Force pumping (with the pump below the water supply) is the only solution.
It was for this reason that Jounama
Pondage was provided. A section diagram of Tumut 3 shows that although
it is an outdoor power station, when
Jounama Pondage is at full service
level (FSL), the alternators and much
of the power station are actually lower
than the level of the water outside,
separated by a thick concrete wall.
The sequence to start pumping is
an interesting one. It goes as follows:
(1) The turbine water inlet valve is
opened and water flows down from
Talbingo reservoir to drive the turbine and alternator, thus generating
full voltage.
(2) The alternator is synchronised
with the state grid.
(3 ) The turbine inlet valve is closed
but the machine continues to rotate,
the alternator now acting as a motor
driven by the state grid.
(4) The pump valve is opened and
water is pumped from Jounama
Pondage back uphill to Talbingo reservoir.
Power to drive the machines when
they are acting as motors is supplied
(via the 330kV state grid) from the
thermal power stations located in the
Newcastle region. This pumping operation is only undertaken very early
in the morning, when the state load is
very light. In these dark hours , it is
economical to keep the thermal stations running to provide the 750MW
pumping power, as large boilers cannot be operated below some minimum load.
Thus, the steam turboalternators
and boilers at Eraring and Bayswater
are kept thermally stabilised, ready
for the morning peak which begins
around 6am. In effect, electricity is
being stored for later use.
Snowy/Murray system
To find the greatest water head of
all hydroelectric plants on the Australian mainland, we must look to the
Murray 1 power station. This is part
of the southern half of the Snowy
scheme - the Snowy-Geehi-Swampy
Plains-Murray development.
During wet seasons, the Murray 1
and Murray 2 power stations are
driven by water caught in the precipi-
,\
TWO 130,'20 TON OVERHEAD
TRAVELLING CRANES
'- EARTHFILL
FOUNDATION - '
EXCAVATION LINE
RL 1197
PUMP SCA l f 01 i lf .
SECTION ALONG TUMUT 3 POWER STATION
RL 1152
Above: this cross-section diagram of
Tumut 3 power station shows how
three of the alternators double as
pump motors. The turbines are
immediately below the alternators,
while the three centrifugal pumps are
right at the bottom. Note that the
tailwater from this power station is
above the turbine, so that the pumps
can operate.
tous gorges of the Geehi River catchment. Geehi Dam, a rock/earth wall
91 metres high, impounds 21.1 gigalitres of water 1106 metres above sea
level (higher than the Blue Mountains).
The overflow spillway for this dam
is unusual. A 32 -metre diameter
bellmouth opens into an 8.84-metre
diameter underground tunnel which
passes under the dam wall. On the
downstream side, this overflow tunnel exits to open air in a flip bucket
which spouts the escaping water upwards to prevent erosion.
Snowy-Geehi tunnel
Another view ofTumut 3 power station, this time from above the headrace. The
high voltage switchyard is in the background.
At times , insufficient rain/snow
falls on the western side of the ranges
but the eastern Snowy River may be
running full. In such circumstances,
water pumped up from Lake Jindabyne flows via the 14.4km Island
Bend-Geehi transmountain tunnel to
refill Geehi reservoir.
In still dryer periods, water is allowed to flow from the Lake Eucumbene mass storage via the EucumbeneSnowy tunnel to Island Bend; thence
under the Great Divide (1000 metres
SEPTEMBER
1Y91
91
provided for two pipes but the third
was added during construction. These
three pipes weigh 13 ,000 tonnes, plus
the weight of water inside.
At any one moment, those pipelines contain 43,000 tonnes of water
rushing downhill at an average velocity of 93km/hour. At a bifurcation before the power station, the three pipelines divide into 10 conduits, each
leading into a turbine.
The 10 vertical shaft Francis turbines, each driven by water at the rate
of 24 tonnes per second, provide a
total of 950MW.
Murray 2 power station
Water is discharged from Murray 1
into the Murray 2 pondage, thence
through a tunnel and pipelines to the
Murray 2 power station, the last and
most western on the Snowy scheme.
This Murray 2 pressure tunnel is
one of the largest in cross section, 7. 5
metres in diameter, steel reinforced
and concrete lined throughout. Four
machines, each rated at 137.5 megawatts, produce 17kV to feed the stepup transformers.
Interstate electricity
This is the Murray 1 power station which has the highest head of any
hydroelectric station in Australia. It has 10 vertical shaft Francis turbines
which provide a total power output of 950MW.
below the mountain peaks above) to
Geehi.
From Geehi reservoir, water flows
westward via the Murray 1 pressure
tunnel towards the Murray power stations.
The flow of water into and out of
Geehi reservoir is controlled by separate valves, immense 7.6 x 3.7-metre
bulkhead gates, stoplogs and guard
gates. The mind boggles at the immense size of these valves - such is
the amount of water used by the
Snowy scheme.
Murray 1 pressure tunnel
The Murray 1 pressure tunnel carries water from Geehi to the heads of
92
SILICON CHIP
the Murray 1 pressure pipelines. Steel
and concrete lined throughout its
11. 7km length, this 6. 93-metre diameter conduit carries 250,000 litres
of water every second!
An 8.2-metre diameter vertical
surge-relief shaft, 114 metres high, is
situated half a kilometre back from
the western end of the pressure tunnel. The top of this shaft opens to
atmosphere into a 61-metre diameter
surge pool situated on the mountainside above.
The pressure tunnel leads through
valves into the three pressure pipelines running 1.5 kilometres down
the mountainside to the Murray 1
power station. The originai design
The Murray power stations were
designed to supply the first major interstate transfer of synchronous electric power in Australia. The Murray
Switching Station is an immense array of 345kV busbars, circuit breakers
and protection equipment. From here,
the outputs of both Murray power
stations are carried by three powerlines to Dederang, where they join the
Victorian grid.
In addition, 330kV interconnections
join the Murray power station to the
Upper Tumut and Yass substations.
These links allow power to be interchanged between the thermal power
stations of NSW near Newcastle and
those in Victoria near Yallourn and
Morwell.
This, the first interstate synchronous interconnection, has since been
extended to South Australia.
SC
.Acknowledgement
Grateful acknowledgement and
thanks to Libby Langford and
the Snowy Mountains Hydroelectric Authority for data, photos and
permission to publish.
|