This is only a preview of the November 1992 issue of Silicon Chip. You can view 52 of the 104 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Items relevant to "A 2kW 24VDC To 240VAC Sinewave Inverter; Pt.2":
Articles in this series:
Items relevant to "An Automatic Nicad Battery Discharger":
Articles in this series:
Articles in this series:
Articles in this series:
|
The Story Of
Electrical Energy, Pt.21
Electric lighting came to Sydney's streets on 8th
July, 1904. Suddenly, at 5.16pm, the city streets
were a blaze of light from Circular Quay to
Redfern & from Hyde Park to Darling Harbour.
By BRYAN MAHER
Back in the new Pyrmont power
station, the Lady Mayoress, Mrs. S. E.
Lees, had turned a gold presentation
key. That simple act had closed the
exciter field circuit of a 5.2kV alternator. This supplied 3-phase AC to new
substations at Town Hall and Lang
Park. At each site, a high-voltage induction motor began to spin, driving
two direct-coupled 240V DC genera-
tars. With the generators in series,
240/480V DC 3-wire circuits buried
under the city's footpaths supplied
231 arc lamps to illuminate the streets.
These 2000 candlepower electric
lamps so overpowered the old gas
lamps that the future of electricity
was assured. Each set of 10 carbon arc
lamps was connected into a series
group which was supplied by the 480V
DC mains. The grounded centre neutral wire was used to provide odd sets
of five series arc lamps with a 240V
DC supply. The carbon rods had a
burning life of only 16 hours and then
had to be replaced.
But we have begun our story in the
middle. Though practical electric
lighting became possible from 1831
followfng the discoveries made by
Michael Faraday in England, Sydney
was then only a struggling convict
Top of page: this photo shows the
interior of Pyrmont power station as it
was originally built, with Ferranti
high speed twin-cylinder steam
engines.
NOVEMBER
1992
79
dangerous, that the electricity leaked
away in the ground, and that it could
cause fires and/or electrocution. These
companies made no mention of their
own dubious installations, where
cables were sometimes just flung over
the roofs of buildings.
As well, there were numerous new
entrants to the field, like the Empire
Electric Company Ltd, whose advertised rate per kilowatt hour (kWh)
forced the council to reduce its tariffs.
And this was before the said company had even commenced operations.
Commercial/domestic supply
Manufactured by Belliss and Morcom, this 300 horsepower twin-cylinder steam
engine measures about four metres long. The engine with its 4-tonne flywheel is
direct-coupled to a Bruce Peebles alternator which once supplied 210kVA at
420V 3-phase to drive the machinery in a biscuit factory. The small generator at
the righthand end is the exciter, which can produce up to 90V DC at 61A to
supply the rotor field coils of the alternator. This 14-pole machine ran at 428.57
RPM & generated a 50Hz AC supply. However, the frequency would not have
been all that stable, regulated as it was by a simple but fairly effective steam
valve governor. The unit is today a working exhibit at the Power House Museum
in Sydney.
village. And even though Sir Humphrey Davy's arc light invention had illuminated the Paris Opera House in
1846, practical electric illumination
had a long gestation period.
The illumination of Sydney's streets
was by oil lamps in 1843, then by gas
three years later. But the city fathers
were slow to adopt electric light.
Other towns were more progressive.
On 8th November, 1888, Tamworth
had the honour of being the first town
in the Southern Hemisphere to have
electrically lit streets. The town of
Young was soon to follow and then
the towns ofLambton, Moss Vale, Broken Hill and Redfern got into the act.
The electricity bill
Moving slowly, the NSW government took 10 years.to pass a bill au~
thorising the Sydney Municipal Council (SMC) to acquire generating plant.
Finally, the council appointed one
Major Cardew as its consultant. He
advised the building of a power station in Kent street to supply an 8km
radius with illumination.
The Kent Street site was resumed
80
SILICON CI-IJP
by the Government due to an outbreak of bubonic plague, so Pyrmont
became the second choice. With incredible foresight, the Council anticipated the coming demand from homes
and private factories. However in entering the electricity supply business,
the City Council faced competition
from five well established private DC
generating enterprises.
At the forefront of this competition
were th_e Oxford Street Electric Light
Company, the Imperial Arcade Electric Light Company, and the Strand
Electric Company whose 100-volt DC
system spread like a spider's web
around the Strand Arcade and adjacent shops.
In the long run, the City Council's
greatest competitor was the implacable Australian Gaslight Company.
Well entrenched for over 60 years before the advent of electricity, the gas
company was a formidable adversary.
A lot of quite unethical propaganda
emanated from the Council's competitors . The private electric companies
spread false tales to the effect that the
council's underground supply was
The Council power also supplied
city buildings and homes where the
new incandescent filament lamps,
invented by Swan in England and
Edison in the USA, were a great boon.
These globes were more suitable for
indoor lighting than arc lamps which
generated lots of heat and copious
quantities of carbon dioxide and other
noxious gases.
City building owners immediately
saw the advantages of lifts powered
by DC motors. These were much
cheaper than the steam powered hydraulic elevators previously used by
the largest companies. Some big city
stores retained their hydraulic lifts
for 50 years or more, simply replacing
the steam engine with a DC motor.
However most new buildings went
straight to electric elevators, many
later changing to the Ward Leonard
control system for more accurate positioning. Little did those people realise that their DC lifts would dominate
electrical supply policy for the next
80 years.
Home owners and tenants in city
apartments quickly saw the advantages of electric appliances. After lighting, there was a big demand for electric irons and European hair curlers,
as in this field gas had no equivalent.
Slowly, electric heating and cooking
replaced gas appliances.
Sydney Municipal Council charged
lighting either at a flat rate of five
pence per kWh or a two-part rate
which cost more for primary units
and two pence for each subsequent
kWh. Power for all motors, lifts, cooking and heating was charged at the
lower rate.
One year's operation saw 86 private and government consumers connected to the DC mains supply, in
Sydney Council linesmen used to do all the work without any heavy machinery.
This photo shows how the heavy cable reels were grappled off the horse-drawn
drays prior to the cable being laid in the trenches.
addition to the street lighting, with a
total loading of just over 1MW. Generating and distribution costs were 1. 99
pence per kWh.
Pyrmont power station
The original Pyrmont station was
equipped with three Ferranti twincylinder high speed steam engines.
Each was direct coupled to a Ferranti
5200-volt 50Hz alternator. Two of
these units were rated at 1000 horsepower (746kW) each, while the third
was rated at 500hp (373kW).
Five Babcock and Wilcocks boilers
supplied steam at 160 psi (1.1 MPa) to
drive the engines. Coal was brought
in by rail (or ship in emergencies),
while cooling water came straight from
Darling Harbour. This installation was
state of the art in its day, with economisers and feed water heaters to increase thermal efficiency.
So fast was electricity accepted in
Sydney town that within 12 months
of Pyrmont opening, additional machinery was ordered to almost double
the original capacity.
The 45km of underground cabling
around the city was extended and the
existing DC substations enlarged. Today, we can only marvel at the speed
at which such work progressed without the aid of heavy machinery. All
trenching was done by pick and shovel
and all carting by horse and dray.
While the City Council was busy
wiring up the city and close surrounds,
a few industries further out set up
their own plants. Some of these were
state-of-the-art AC systems. One notable engineering effort was installed
in a biscuit factory.
AC/DC system
True to the preferences of Thomas
Edison, and with lift motors in mind,
Sydney Council supplied all the in-
ner city with a 240/480V 3-wire DC
system. But the AC/DC rotary substations were expensive to install and
operate. Therefore, the outer city areas were supplied by 240/415V AC
mains from transformer substations
at Darlinghurst, Athlone Place and
the power station itself.
This was the first normal AC supply for Sydney horn:es. In outer city
regions, streets were lit by the same
arc lamps as in the city, except that
groups of nine lamps were arranged
in series across the 415V AC mains.
Thus electricity was ushered into
Sydney as two incompatible systems :
DC and AC. This dichotomy was to
persist for more than 80 years, until
1986, often to the despair of city
shopkeepers.
As late as the 1950-1960 period,
some business establishments in York
and Clarence Streets still operated on
the 240V DC supply. The custom was
for electrical businesses to provide
their own motor generator set to provide 240VAC 50Hz, so that radios and
NOVEMBER
1992
81
DC in the inner city caused Sydney
Municipal Council to upgrade its biggest and longest lasting DC substation
in Clarence Street. Originally installed
in 1904, this substation used high volt. age induction motors driving series
connected pairs of DC generators.
Later, rotary converters generating 240
volts DC were connected in pairs to
give the 240/480 volt 3-wire supply.
The first mercury arc rectifiers were
installed in 1933.
Mercury arc rectifiers
This photo shows three of the 36 600kW mercury arc rectifiers installed in the
Clarence Street substation in 1959. These mercury rectifiers used six anodes, for
3-phase full wave rectification. The cubicles underneath them house auxiliary
equipment and the cooling fans.
appliances could be demonstrated.
Problems came with television, because the in-house AC supply was
usually of uncertain frequency. Any
deviation from the nominal 50Hz
caused drifting hum bars on the
screens of early TV receivers, to the
consternation of shop owners and prospective customers.
So fast was the electrical growth in
1904 that within three years an extension was added to Pyrmont to house
new more efficient machinery, thus
reducing the cost per kWh. The City
Council then shocked its competitors
by dropping the council's rate from 2
pence to 1.5 pence per kWh. Subsequently, each private electric company
asked the council to buy it out as they
could no longer compete.
The goodwill of four companies was
eventually purchased by the Council
for a total of 110,375 pounds, each in
proportion to its yearly unit sales.
The largest was the Strand Electric
Lighting Company which had been
selling 1.24 million kWh units annually. The Council then refurbished those
customers' installations to bring them
up to 240V standards.
Legal tussle
A legal tussle, previously unheard
of in Australia, ensued in 1905. The
new Royal Hospital for Women, in
Oxford and Young Streets, Padding82
SILICON CHIP
ton, was designed and built assuming
an electricity supply. It was four storeys high and electric lifts and lights
were essential for safety reasons.
But Paddington Council wanted to
charge Sydney Municipal Council
rates for the narrow land corridor occupied by the high voltage power line
to the hospital. Further argument
raged over a substation site. Sanity
eventually prevailed; the substation
was built within the hosp.ital and
agreement between the councils was
reached.
Sydney Council mounted an intensive campaign to electrify the city.
Arc lamps were hired out to commercial users who could not afford the
purchase price. Similarly, businesses
could rent DC motors in any size from
375 watts to 22.5 kilowatts. The small
units were 240V types, while the larger
units ran off the 480V supply.
The conservative rates charged encouraged businesses to hire a total of
361 motors in the first two years of
the scheme. More than 50 different
types of factories and stores took
advantage of this facility.
Three years after its commencement, the Council undertaking had
1600 customers using 6 million kWh
units annually. And the system was
growing daily, taxing the power stations' 6.7MW installed capacity.
The increased use of 240/480 volt
On 1st June 1959, the substation
was changed over to mercury arc rectifiers exclusively. Six sets of six
600kW glass bulb mercury arc rectifiers with main and interphase transformers and accessories were provided. When placed on load, the mercury arcs bathed the interior of the
cabinets in a beautiful (but dangerous)
violet glow. Together, the 36 mercury
rectifiers could deliver 7300 amperes
DC.
The large glass bulbs came by sea
from Hersham in England, the final
shipment arriving in early 1959. During shipment, the bulbs were suspended in a large timber crate using
ropes and steel springs. The bulbs
were shipped upside down with the
large quantity of mercury sloshing
about in the head of the condensing
chamber.
In Sydney, each glass vessel was
mounted within a steel cabinet, its
mercury cathode at the bottom and
the condensation void at the top. Each
glass vessel had anode arms with external copper plated molybdenumiron alloy contacts. These connected
via the glass/metal weld to join the
dense graphite anodes inside. The
glass arms each provided a separate
pathway for the mercury arc from the
cathodic pool at the bottom to each
graphite anode. This isolation prevented any chance of a flashover between the AC anodes of any two adjacent phases.
The auxiliaries consisted of a cooling fan and starter electrodes for each
glass bulb. The fan was automatically
speed controlled by passing its AC
supply through a saturable reactor.
These were commonly used to control AC currents before the days of gas
thyratrons or Triacs and SCRs.
A saturable reactor is an iron-cored
inductor with two AC windings and a
DC winding. The AC windings car-
ried the current to the fan while the
DC winding carried the output current from the mercury arc rectifier.
When the rectifier was supplying little output current, the inductance of
the AC windings was so high that the
fan would not run.
As the rectifi er was called upon to
supply more current, that current
passed through the DC winding of the
saturable reactor. This increased the
magnetising force in the iron core and
so reduced the reactance of the AC
windings. This in turn increased the
AC voltage to let the fan run.
At full DC load current in the rectifier circuit, the reactor core would be
completely saturated, cancelling all
the inductance of the AC windings
and allowing the fan to run at full
speed. Thus, the fan speed was automati cally varied to give the right
amount of cooling at all times.
Exciter circuit
When first switched on, the rectifier bulb contained cold mercury. To
initiate an arc and thus ionise the
liquid metal, a magnet pulled down a
spring arm within the bulb to make
contact with the mercury. That passed
a current into the mercury.
A second magnet would then attract the spring arm upwards , drawing an arc sufficient to initiate ionisation. To maintain ionisation, even with
no load current, two subsidiary electrodes continually maintained a sma 11
arc to the mercury surface.
Because the cathode mercury pool
must be the positive output terminal,
there is no such thing as a negative
output 6-phase glass rectifier. Therefore, in a 3-wire positive/zero/negative DC system, the negative 240V DC
bus must originate at the transformer
secondary star point.
To obtain balance in the 480V /240V
system, the council linesmen would
connect some lighting circuits between positive 240V DC and zero.
Other circuits would be connected
between zero and negative 240V DC .
With roughly equal loads on both
sides , only a small difference current
would flow in the zero line returning
to the substation. Motors and other
heavy loads were made for a 480V DC
supply and were thus connected between the +240V and -240V lines.
Because th e major lo ad current
flowed out on the +240V line and
returne_d via the -240V line, four recti-
This photo shows smaller mercury arc rectifiers than were used in the Clarence
Street substation. These units have only three anodes and a somewhat lower
current rating.
fiers out of the six were used in parallel to supply this current. The fifth
and sixth rectifiers of a set provided a
zero centre line potential.
Each set of six rectifiers could supply 1215 amps continuously, or 1520
amps for a 2-hour peak period. In
addition, heavy loads of up to 2430
amperes mulrl be supplied for up to
15 seconds , allowing the starting of
large motors anywhere in the city.
Out-of-balance current in the zero line
could be as high as ·1 20 amperes indefinitely.
As late as 1986, Sydney City still
drew just over 4000 amperes from the
last remaining three sets of glass rectifiers.
Apart from their high efficiency,
these mercury arc rectifiers were designed for zero maintenance. They
had no moving parts, the critical components were sealed under vacuum ,
and neither the mercury nor the graphite anodes deteriorated during full
load operation. These rectifiers thus
had a very long working life.
You might ask why so much DC
load still existed in Sydney as late as
1986? In truth , much of that load exists to this day but it is now hidden.
The advent of the AC supply in later
years saw the replacement of most DC
machinery with 3-phase squirrel cage
induction motors. But from the very
first days, DC motors were found to be
superior for controlling city lifts and
indeed this is still the case.
Many buildings in York, Clarence,
George and Pitt Streets, as well as
around the waterfront area, date from
early days before modern building
standards were in force. Any attempt
to rebuild the lifts in these buildings
to modern design using AC motors
would be very costly. Therefore, the
DC driven lifts remain to this day, and
will probably continue for years to
come.
By the mid 1980s, the advent of
high current solid state rectifiers allowed building owners to install their
own rectifier systems to run from 415V
AC mains. But until 1986, the supply
authority, Sydney County Council,
was obliged to maintain the 480/240V
DC reticulation throughout the city.
Thus Clarence Street substation remained a_s a supplier of DC for 82
years.
Acknowledgement
Special thanks to Phil Parsonage
and Des Barrett, and grateful acknowledgement to the staffs of Sydney El ectricity, Pacific Power and the Museum
of Applied Arts and Sciences, and to
Gordon Anderson.
SC
NovEMB EH
1992
83
|