This is only a preview of the September 1992 issue of Silicon Chip. You can view 51 of the 104 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Articles in this series:
Items relevant to "A General-Purpose 3 1/2 Digit Panel Meter":
Articles in this series:
Articles in this series:
Articles in this series:
|
The Story of
Electrical Energy, Pt.20
One year after Sydney's Ultimo power station
was built, the growing electric tramways had
exceeded its capabilities. Massive extensions to
the power house together with AC reticulation &
AC/DC substations solved the problem.
By BRYAN MAHER
The Sydney electric tramway system had expanded so quickly by 1900
that voltage drop problems in the 600V
DC feeders were acute. Both the
Ultimo power station and the 600V
feeder system were fast approaching
their capacity limits.
The 1900 figure of 100 electric tramcars running over the 50km of track
88
SILICO N CHIP
was expected to be doubled almost
yearly. An additional ten 600V DC
feeders laid in 1901, reaching out eight
kilometres from the power station,
were only a bandaid solution. Massive extensions were called for, including a rethink of the whole system.
As electrical technology was ad-
vancing fast, it was decided not to
build further DC generators but to
adopt 3-phase AC. The designers, to
their everlasting credit, decided to
think big! A new engine room was
called for, double in length, width
and height compared to the original
buildings. Plans were made and, in
1902, foundations were laid for six
very large 2-cylinder vertical steam
engines.
Each was to be direct-coupled to a
1.5-megawatt AC generator. Each 2300
horsepower (1.72MW) engine was
designed to supply a 50% overload
for the 3-hour peak periods twice a
day. By 1904, three of these engines
were installed and running.
The vertical 2-cylinder steam engines were single expansion cross-
Facing page: this view of the Ultimo
power house shows the three huge
condensing steam engines and their
alternators which rotated at 75 revs
per minute. It must have been an
impressive sight to behold.
compounded condensing units. They
towered 18.2 metres from top to bottom, although one third of this height
was below floor level. That still left
the top of the low pressure cylinder
reaching 12.2 metres above the engine room floor. The rotors of the alternators were so heavy and so large
in diameter that they did double duty
as flywheels.
The construction of each alternator
started with an enormous cast iron
flywheel 7.1 metres in diameter, with
a rim 915mm wide. Forty DC magnetic field poles were then added
around its periphery. These poles were
built up of sheet iron punchings, insulated , and wound with 26mm x
3.175mm copper bar, wound on edge
on an insulated frame. The 40 fieldpole windings were connected in series, resulting in a total field resistance of just 0.5-ohm.
Measured over the field poles, those
rotors were 8.85 metres in diameter.
Each rotor weighed 98 tonnes without the slipring assembly. Add this to
the 20-tonne crankshaft and you had
120 tonnes of machine parts flying
around at 75 rpm. In fact, the peripheral speed of the rotors was 125km
per hour - incredible figures for 90
years ago!
In each machine, the rotor was
mounted on the middle of the crankshaft, midway between the enormous
cranks of the high and low pressure
cylinders. The crankshaft, more than
half a metre in diameter and over six
metres long, was a massive piece of
drop forged and machined steel. The
high pressure cylinders were large
enough at 813mm in diameter but the
low pressure cylinders were enormous, with an inside diameter of over
1.6 metres.
Each complete engine-alternator
combination was undoubtedly the
mightiest machine most Australians
had ever laid eyes upon. Each one
weighed a total of 450 tonnes. Three
of these Allis-Chalmers-ReynoldsGeneral Electric engine generator sets
The new alternators at Ultimo power station used up to the minute technology.
Previously, all electric generation in Sydney had been 600V DC. Note the size of
the low pressure steam cylinder. This had a piston diameter of 1.6 metres.
were installed in Ultimo power station. Work had commenced on the
building and the machinery foundations in early 1901 and all three machines were running under load just
29 months later, in May 1903, a truly
remarkable performance!
As the photos show, these machines
were truly gigantic - the biggest machines in the southern hemisphere,
in fact! Even to this day, the Ultimo
engines numbers 5, 7 and 9 hold the
record as the biggest reciprocating
engines ever installed south of the
equator. Interestingly, only three of
the planned six machines were in-
stalled because reciprocating engines
were overtaken by new technology
within a decade,
New boilers
To provide steam for the three new
engi nes, 24 extra boilers were installed. These were housed in the
boiler house extension, a giant structure which towered over the original
buildings.
They were Babcock, and Wilcox
water tube boilers, each rated at
186kW (250 horsepower) and generating steam at 150psi (1.1 megapascals) and 240°C. These were a great
SEPTEMBER1992
89
advance compared with the original
units which were just three years
older.
Coal was fed to the boiler by a new
invention, the automatic chain grate
stoker. A small steam engine drove
the stoker which effectively became
the moving firegrate. Continuous
movement of the grate finally tipped
the spent ash and clinker down via a
chute to ash trucks below. High above
the boilers, an enormous bunker held
2500 tonnes of coal.
Sixty boilers were planned, in two
rows of 15 on each of two floors.
Extra new pumps provided feed
water for the boilers and circulating
water for the engine condensers. The
boiler house extension was done in
two stages so that the old boilers could
continue steam supply until half of
the new units were installed. When
the new southern end structure was
completed and operating, the original
boilers were demolished and the old
boiler house extended vertically so
that a complete matching facade was
achieved.
The extensions used 3-million
90
SILICON CHIP
bricks to create a building 54 metres
long by 30 metres wide.
Near the middle of the south half of
the boiler house, two giant new chimneys were erected, 69 metres high.
Measuring 7.3 metres square at the
base and 3. 7 metres internal diameter
at the top, each chimney was capped
by a 7-tonne cast iron crown. For the
next 70 years, these structures dominated Sydney's western skyline.
Coal brought from five different
areas by tail way was crushed and then
lifted by a chain elevator with 288
steel buckets to the storage hopper
above the boiler room. Driven by a
large DC motor through a reduction
gear train, the elevator had a capacity
of 40-tonnes per hour.
High voltage alternators
Not only were the alternators very
large, they also produced very high
voltages for the day - 6600 volts AC.
The stationary armature coils were
wound with square insulated copper
(10.2 x 10.2mm), then insulated overall by nine layers of half-lapped 178
microns thick linen tape. Each layer
This view of the Ultimo power station
shows the alternators which were
installed at a later date. Even so, the
size the of the three original
alternators and their condensing
steam engines was never to be
challenged.
was baked, varnished and baked again,
six times in succession. The 6kV insulation made by this simple method
was reliable and long lived.
Lead-sheathed oiled paper insulated cables of 3-core construction
carried the current from the alternators to the 13-metre long switchboard.
Sixteen panels of blue Vermont marble served the three generators, exciters and the original ten 6.6kV outgoing feeders.
The high voltage circuit breakers
were something new in Australia. A
series of brick compartments lined
with opalite had cast iron doors at
front and soapstone slabs on top. Each
such chamber contained one pole of a
6.6kV circuit breaker.
Each pole consisted of two isolated
sets of sprung copper contacts, arranged in pairs (like your thumb
touching your first finger). To close
the switch, a moveable copper bar of
triangular cross section was raised to
bridge all the contacts.
The live moving copper bar was
actuated by an impregnated wooden
rod , connected by other rods and bell
cranks to a grounded metal handle on
the front panel. The whole contact
assembly was immersed in a tank of
heavy mineral oil which extinguished
the arc as the current passed through
the AC zero voltage point.
AC to DC substations
The 6.6kV AC from Ultimo power
station allowed longer transmission
distances but it then had to be transformed down to a lower AC voltage
and converted to DC to supply the
trams. For this purpose, five tramway
substations were built at Macquarie
St (City), Newtown, Waverley, Randwick and North Sydney.
Two underground high voltage cables were laid to each substation by
the British Insulated Wire Company.
These oiled paper insulated cables
were lead-sheathed and the lead
sheathing was grounded to earth electrodes at both ends and at intervals of
about 800 metres along their length.
The shortest run was tci the city substation (2.9km) and the longest to
North Sydney (6.4km). A 732-metre
section to North Sydney was laid on
The Ultimo power station had Gothic proportions, with the men in this photo
giving some idea of the scale. The massive switchboard is situated at the far end
of the building.
the floor of Sydney Harbour and is
thought to be the first high voltage
submarine cable laid in Australia.
This underwat er section , from
Dawes Point to Blue's point, had extra
steel armouring but also contained
three submerged joins. This was because the technology of the day in
England could not produce cable
lengths greater than 185 metres.
Arc-gap voltage surge arresters were
fitted to .the cables, to flash over if a
switching surge or lightning ground
The chimney stacks of the Ultimo power station
dominated Sydney's skyline for many years but
they are now long since demolished. The main
building still survives however and now houses
the Powerhouse Museum.
current elevated the voltage momentarily above 15kV.
At each of the five substations , the
6.6kV supply was transformed down
by air-blast cooled delta-delta transformers to 375V. This was fed to rotary converters which produced 600V
DC to supply all trams in the section.
Initially, 450kW and Z00kW converters were installed. But so fast did the
system grow that within a few years
larger units had to be provided. The
largest were the 1.8MW machines installed at the new city substation at Jamieson Street.
A rotary converter looks
somewhat like a big DC
generator with commutator and brush gear but
without any mechanical
drive. Instead, the AC electrical input is conducted
by sliprings and brushes
to connections on the back
of the armature winding.
Readers are probably
aware that in any DC machine the armature winding always carries AC , this
"being mechanically rectified by the rotating commutator and stationary
brushes. This fact is used
in rotary converters, the armature rotating at a speed
in synchronism with the
AC supply. The 600V DC
output taken from the comSEPTEMBER 1992
91
This photo shows the interior of North Sydney substation as it was in 1902. It
included three rotary converters, each rated at 1200A. In the left foreground are
the three switchboard sections controlling the DC side of the converters. At the
top are the automatic overcurrent circuit breakers, below that the dynamic
ammeters and below them the two open blade knife switches for each machine.
mutator by the brushes then fed the
tramway system.
With the incoming AC at a frequency of 25Hz, the 6-pole rotary converters ran at 500 rpm. Mounted on
the back end of the shaft of each converter was a 30kW 4-pole induction
motor intended for starting the converter and bringing it up to synchronous speed.
Later, these pony motors were dispensed with and the converter started
as an induction motor from low voltage taps on the transformer, through
limiting inductances. A third method
was to start the converter from the
substation battery.
Dynamic ammeters
The large ammeters of the day, with
a scale up to 400mm long, demanded
strong field magnets. Lacking powerful permanent magnets, manufacturers used 600V DC electromagnets instead. To desensitize the meter against
voltage fluctuations, the iron cores
were driven hard into magnetic saturation. This was ingenious!
Should a machine circuit breaker
trip on overcurrent, the operator
would stand on a rubber mat and: (a)
open the blades of the knife switches;
(b) close the circuit breaker; and (c)
slam the bare knife switches closed
by the handle, at the same time being
92
SILICON CHIP
prepared to duck and jump sideways
quickly should that closure cause the
circuit breaker to trip again.
Any circuit breaker opening on
over-current could rain down red hot
globules of the copper or carbon contacts. Also, the breaking of a high
current arc made a thunderclap noise
loud enough to scare the living daylights out of the unfortunate operator.
600V batteries
Most of the substations were fitted
with one or two 600V batteries, each
consisting of 280 lead-acid cells. Constructed of lead lined timber and containing nine positive and 10 negative
plates, each cell contained 125kg of
sulphuric acid electrolyte. Heavily
coated timber bearers and glass insulators supported the batteries.
Rated at 500 ampere-hours, these
batteries could supply up to 1000
amperes for short periods. They were
used to supplement the converter output to the trams during peak periods,
as well as for far-off-peak supply when
the converters could be shut down.
Charging and discharging of the
600V battery was controlled by a
clever differential booster generator.
This machine had its shunt fields
separately excited by the 600V bus bar
and was driven at a constant speed by
a separate DC motor. When there was
no tramway load on the substation
converters, the booster armature generated 100V. This was added to the
600V bus bar supply to give 700V and
charged the battery at 500A.
The booster series field was connected in series with the rotary converter, so that series field opposed the
booster's shunt field. This meant that
when the rotary converters were supplying heavy tramway load, the
booster generated less voltage, and so
the battery charging current pulled
from the rotary converters was correspondingly reduced.
During peak hours, heavy tramway
loads would occur, often of 3000A to
4000A, such as when 30 trams started
simultaneously. Under such a condition, the booster's differential series
field would completely overcome its
shunt field so that the voltage generated by the booster would reverse.
Thus, the charged battery, in parallel with the rotary converter, would
share the tramway load. In this way,
the load fluctuations on the rotary
converters were reduced.
Despite the expense of providing
substations, rotating conversion machinery and the trained staff to tend
them, the new AC/DC system proved
economical. The interest paid on loans
raised to finance the project was less
than the calculated cost of power
which would have been lost in feeder
voltage drop had the DC transmission
system been simply extended.
Sydney continued to have an insatiable need for more and more electric
traction. Between 1900 and July 1904,
electrified track mileage had quadrupled to 192 kilometres, while the
number of trams had grown to 500.
This rate of expansion continued for
years and at the same time Sydney
people wanted electric appliances and
lights in their homes and streets. Many
more power stations had to be built in
the years to come.
Acknowledgements
Grateful thanks for photographs
domi,ted by SRA Archives, the Trustees of the Sydney Museum of Applied Arts and Sciences, and the Public Works Department of NSW. Acknowledgements to Don Godden et al
in "Ultimo Power House; Report on
its History and Technology"; also to
Victor Poljanski, Arthur Perry, P.
Smythe, P. Tweedie, T. P. Strickland
and W. Upton.
SC
|