This is only a preview of the August 1993 issue of Silicon Chip. You can view 27 of the 96 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Items relevant to "Low-Cost Colour Video Fader":
Articles in this series:
Articles in this series:
|
KECK OBSERVATORY
The world’s biggest
optical telescope; Pt.2
Last month, we gave the background to the site
selection and segmented design of the 9.84-metre
Keck Telescope. The guiding force for the project
was Jerry Nelson who had the job of promoting
the concept & convincing enough people to give
financial grants to allow it to proceed.
By BOB SYMES
Ultimately, he was successful in
convincing the astronomers and accountants that the challenge could
be met, and the problems overcome.
Armed with a $US70 million grant
from the W. M. Keck Foundation, Nelson and his collaborators set to work.
The California Institute of Technology
and the University of California made
up the difference in the projected cost
of $US94 million.
These two institutions will run the
telescope through the California As6 Silicon Chip
sociation for Research in Astronomy
(CARA), an association inaugurated
specifically for this purpose. Through
CARA, they will allocate the major part
of observing time, though the University of Hawaii will receive 10% of the
time as co-ordinator of the science
reserve atop Mauna Kea.
On September 12th, 1985, the
ground-breaking ceremony took place
on the summit and the dome and associated complex was completed in
October 1988. The tube and supporting
structure was contracted out to the
civil engineering firm of Schwartz and
Hautmont of Tarragona, Spain and was
also completed in 1988. It was erected
on the summit in 1989.
Understandably, the mirrors caused
the major headaches. At every step of
the way problems arose and had to be
overcome.
Since multiple mirrors, when used
together, cause optical diffraction
effects if they remain as individual
round segments, it was necessary to
construct hexagonal segments that
nestle into each other to minimise the
effect. Under certain circumstances,
such as when two telescopes are used
as an optical interferometer, it is these
very diffraction effects that are used to
extract information about the object
under study, but when the telescope is
used on its own, the diffraction spikes
can hide details that might otherwise
be observed.
A further effect of diffraction is
that contrast is reduced, thus further
hiding subtle detail. Squares, triangles and hexagons are the only shape
of mirror that can nestle together in
this fashion. From the point of view
of wasted material and keeping the
shape as nearly round as possible to
make figuring easier, a hexagon shape
was chosen.
And this is where the problems began. Normally, a mirror is ground and
polished in its final (usually circular)
shape. But a new technique, known
as stressed mirror polishing, was to
be attempted. In this method, the
polishing table has a series of suction
pads and rams which distort the blank
before polishing begins. The mirror
is then polished to a spherical figure,
and when it is released from the table,
the correct hyperboloidal figure would
be obtained.
Terry Mast, the University of
California optician who over
s aw
most of the design and construction
of the mirrors, determined that the
correct shape would not be realised
unless the blanks were polished in
the round and then cut to hexagons,
rather than the other way around.
The danger was that when cut, internal stresses in the blank would
be released, thus throwing out the
carefully created profile.
Less of a problem, but still requiring
careful attention, was that since each
of the 36 mirror segments has one of
six possible different surface profiles,
dependent on where it will be in the
final mosaic, the radial position of
the hexagonal sides had to be in exact
relationship to the figure.
Optics fabrication
Itek Optical Systems of Lexington,
Massachusetts was chosen to fabricate
the optics, as they had much experience in satellite optical systems. The
first six segments were to be delivered
by late 1987 and the following 36
(which included six spares – one for
each position) were to be made available within two years. However, by
late 1987, work was still being done
on the first segment and by mid- 1988
the second was giving trouble.
The feared stress-relief distortions
had materialised and each segment
had to be individually touched up under computer control, optically tested
using a laser interferometer, and then
touched up again, until the residual
errors were within the ability of the
This diagram shows the
location of the 36 segment
primary mirror, the
secondary (2) and tertiary
(3) mirrors and the Nasmyth
(4) & Cassegrain (5) foci. The
tertiary mirror is required
for the Nasmyth focus but is
removed to allow light to pass
through a hole in the primary
mirror to the Cassegrain focus.
warping harness on the tele
scope
mirror mount to correct.
As a result of this delay, in 1989
CARA contracted another optical
laboratory, Tinsley Laboratory of
Richmond, California, to take over
the construction of half the mirror
segments. Work was under way by
February.
Both the Tinsley and Itek blanks
were “hexagonised” at the Itek works,
and by mid-1989 two segments per
month were being produced between
the two contractors. By this time, it
had been decided to forego the computer controlled zonal refiguring, since
this was proving too slow, and it was
hoped that the warping harness could
cope with the now greater residual
aberrations. In fact, the after hexing
deformations have been reported to
be as great as 1 micron.
The warping harness is a series
of adjustable springs on the support
structure of each mirror. There are
30 such springs for each segment and
when correctly set, they can reduce
the residual aberration by a factor of
up to 15.
At least the delivery was easy, unlike the delivery of the great primary
of the 5-metre Hale telescope which
made a slow journey from the Corning
Glass works in New York to the west
cost on a specially constructed flatbed railcar. By contrast, the mirror
segments for the Keck were shipped
from Lexington, Mas
sachusetts to
Honolulu by Federal Express! They
were then sent by barge to Hilo on the
windward side of the Big Island and
by truck to the summit. The relatively
low weight of each segment made
this method quite feasible, something
that couldn’t be said of the massive
Hale mirror.
In common with most observatories,
there is a re-aluminising facility in the
building, so that the mirrors do not
need to leave the mountain when the
reflecting surfaces need to be refur
bished. In fact, they were delivered
from the mainland uncoated and were
aluminised just prior to installation.
Each mirror is housed in a complex
support that includes adjustable pads,
feedback sensors and actuators, as well
as the preset warping components. The
requirement is that every segment is
supported in such a way that all act
together to form one 10-metre mirror.
Each segment be in perfect collimation
with all the rest in the mirror support
framework and must be able to correct for the inevitable tube flexure of
a structure as large as this when the
August 1993 7
movement is in the order of 1mm, in
increments of 0.004 microns. The position actuator consists of a precision
ground screw of 1mm pitch. Shaft
encoders allow the screw to be turned
in increments of one ten-thousandth of
a revolution. This 1mm per revolution
displacement is further reduced by a
factor of 24 by a ratio-reducing hydrau
lic bellows unit.
Capacitive feedback sensors
This view, taken from within the tubular structure of the telescope, shows all
the mirror segments in place. In all, some 36 hexagonal segments are used to
create the primary mirror.
telescope is slewed from one part of
the sky to another.
Flexure of the tube has been estimated to be in the order of 0.5mm as
the telescope is pointed in different
directions, and this flexure has to be
reduced by a factor of 10,000 in order
to maintain the perfect collimation
required to give the sub arc-second
images that the site is capable of producing. The actuators are also capable
of detecting and correcting thermal
changes in the mirror and support
structure.
Mirror support system
In order to provide this required
collimation, the mirror support system
comprises passive and active support.
The passive support is made up of a
stainless steel hub and disc (the flex
disc), which sits in a circular cutout
in the rear of the mirror and prevents
the mirror moving laterally from its
assigned posi
tion. Support for the
mass of each mirror is by means of
three “whiffletrees” evenly spaced
about the mirror, and about two thirds
8 Silicon Chip
of the way out from the centre – at the
radial centre of mass of the segment.
Each whiffletree contains a further
12 floating supports, giving a total of
36 floating supports per segment. The
principal is similar to the technique
used by thousands of amateurs for
their home-made telescopes, only
mechanically far more complex and,
of course, on a completely different
scale. Effectively, each mirror segment
is able to tilt or shift to counteract the
previously discussed errors.
By the way, the word “whiffletree”
comes from the days of stagecoaches,
where the whiffletree was the pivoting
wooden cross-arm attached to the drag
spar. By pivoting, it compensated for
any uneven pull by the horses on either
side of the spar.
Each mirror segment, thus being
able to move freely within its lateral
confinement, allows the active control
system to tilt or move it toward or away
from the focus in order to maintain
collimation. Each segment has three
position actuators associated with
it, one on each whiffletree. The total
Feedback for the actuators is supplied by temperature com
pensated
displacement sensors, consisting
of parallel plates mounted on each
mirror, with a third plate, called
the paddle, attached to the adjacent
mirror, placed between the first two.
The change in capacitance induced
by any relative shift between the two
mirrors is detected and the resulting
corrective commands are sent to the
position actuators.
Each internal segment has 12 sensors attached to it and each peripheral
segment has six or eight, depending on
whether it is a corner or side segment.
The sensitivity of this system is such
that displacements of the order of
0.001 microns can be detected. Jerry
Nelson states that there are actually
63 more sensors than are required
to define the mirror shape, so there
is sufficient redundancy to keep the
telescope functioning to specification
even if there are some sensor failures,
assuming those failures are randomly
distributed around the various mirrors.
This also gives the ability to switch
out a (faulty) sensor that is returning
readings that are substantially different from its neighbours, whilst still
allowing the telescope to operate normally. This is similar to the multiple
sensor “democratic” systems used on
aircraft computer controls. He further
comments that a great advantage of
the active control chosen is that it
relies on no external source to define
its parameters. When the telescope is
switched on, it corrects itself and is
ready for work.
This can be done at any time, day
or night, or even with the dome slit
closed. Thus, engineering calibration
or work can be carried out when ever
it is convenient. This contrasts with
some active systems, where a star or
artificial equivalent has to be viewed
and its image analysed before the
appropriate commands can be issued
to the correcting mechanism. False
incoming data, such as air-column or
dome turbulence that scatters the incoming star image, is therefore entirely
eliminated.
The information received from the
168 sensors, the correc
tive calculations and the correction commands
to the 108 actuators are handled by
12 microcomputers under the overall command of a DEC Micro-VAX.
Corrections are performed every half
second, with a 10-second settling
time required after a major slew of
the telescope. One of the computers is
dedicated to maintaining a log of all
readings and subsequent actions, so
that if anything goes wrong, its data
can be analysed to isolate the problem.
An example would be where a wire
or actuator rod breaks. The computer
would sense an alignment problem,
send a corrective command, and fail
to see a response from the displacement sensors. Obviously a runaway
condition is then likely. Whilst such
conditions can be trapped by the software, by keeping an activity log, the
actual source of the problem can be
quickly identified.
Secondary mirrors
There are two interchangeable secondary mirrors that result in overall
focal ratios of f/15 and f/25. The f/15
secondary is 1.45 metres in diameter
and is intended for work in the visible
spectrum. The f/25 secondary is 51cm
in diameter and is designed for observation in the infrared region.
The f/15 secondary mirror was
ground and polished at the Lick
Observatory optical laboratories in
Santa Cruz, California, under the
guidance of master optician David
Hilyard and astronom
e r Joseph
Miller, who described it as the most
difficult grinding job they had ever
undertaken. The mirror is made of
Zerodur, is hyperboloidal in figure
and, because of the very small focal
ratio of the optics, is highly convex
(the radius of curvature is only 4.7
metres). As a result, special flexible
polishing laps had to be devised, and
progress constantly monitored with a
laser profilometer, which could detect
aberrations of the order of λ\2. After
final figuring, testing by more elaborate optical methods indicated a figure
of better than λ\15.
The finished mirror was shipped to
Hawaii on July 19th, 1991. The optical
Great care must be taken in polishing & figuring the mirror blanks & this is
done before they are hexagonised. Here an optical technician uses a laser
profilometer to check a mirror blank.
combination of the f/1.75 primary
and the secondary yield a final f/15
focus. This secondary will be used for
observations at visible wavelengths.
A further complication that occurred
during the polishing of this mirror was
its disturbance on the polishing table
during the San Francisco earthquake
in October 1989. Luckily no damage
was sustained and re-alignment was
successfully carried out.
The f/25 secondary is made of nickel-plated beryllium. It was figured at
the Lawrence Livermore National
Laboratory near San Francisco, tested
and finally plated with gold. It will
be used exclusively for work in the
infrared spectrum and has the ability
to be used as a “chopper”, mechanically moving to alternately provide a
view of the object being studied and
the background sky. In this way, sky
readings can be subtracted from “object + sky” readings to give an “object
only” output from the detectors.
Each secondary mirror is housed
in its own secondary support which
can be placed interchangeably forward of the prime focus as required.
Both supports have the same external
August 1993 9
This photo shows the complex support structure of the main mirror. Each
mirror segment is monitored & adjusted by the computer control system twice
every second.
shape as the main mirror mosaic to
minimise the effects of diffraction
and also to minimise the central obstruction. They block only 9% of the
incoming light.
Both secondaries will deliver their
light to either the Cassegrain focus
behind the primary mirror – the central hexagon being left out to provide
access to this focus – or via a flat ter-
tiary mirror placed in line with the
mechanical axis, and at 45 degrees to
the light path, to a focus at one of six
locations around the telescope. Two of
these locations pass through the axis
bearings to two Nasmyth platforms,
where bulky or heavy equipment can
be accommodated without affecting
the fine mechani
cal balance of the
system. The other four are for lighter
Table 1: Telescope Facilities on Mauna Kea
Facility
Size
Primary Use
University of Hawaii 24-inch Telescope #1
0.61m
Optical
University of Hawaii 24-inch Telescope #2
0.61m
Optical
University of Hawaii 88-inch Telescope
2.24m
Optical/Infrared
NASA Infrared Telescope Facility
3.0m
Infrared
Canada-France-Hawaii Telescope
3.6m
Optical/Infrared
United Kingdom Infrared Telescope
3.8m
Infrared
Carltech Sub-Millimetre Observatory
10.4m
Millimetre/sub-millimetre
James Clerk Maxwell Telescope
15m
Millimetre/sub-millimetre
W. M. Keck Telescope
10m
Optical/Infrared
Table 2: Facilities Planned Or Under Construction
Facility
Size
Primary Use
Second keck Telescope
10m
Optical/Infrared
VLBA Facility
Subaru Telescope
US-Canada-UK National Optical Telescope
Radio
8.3m
Optical/Infrared
8m
Optical/Infrared
Smithsonian 6-Antenna Array
Galileo National Telescope
10 Silicon Chip
Radio
3.5m
Optical/Infrared
instruments that can safely ride in the
tube itself.
In addition to standard observatory
instrumentation, five major instruments are being built specifically
for use on the Keck telescope to take
advantage of its unique capabilities.
They are:
(1). The Low-Resolution Imaging
Spectrograph (LRIS), a collimated array of four 2048 x 2048 CCDs imaging
an area of 6 by 8 arc-minutes at prime
focus. Used in the 0.4-1.0µm region of
the spectrum, its angular resolution is
0.15 arc-seconds.
(2). The High Resolution Echelle
Mosaic Spectrograph (HIRES). This
is similar in construction to the low
resolution spectrograph but the spectral resolution is 10 times higher and
it works in the 0.3-1.0µm region.
(3). The Long Wavelength Spectro
graph (LWS), a 96 x 96 BIB (Bumped
Indium Bond) array used in the
8-20µm region.
(4). The Near Infra-Red Camera
(NIRC). Covering the 1-5µm spectrum,
it uses a 256 x 256 indium antinomide
array with an angular resolution of
0.15 arc-seconds. It was developed
at Caltech.
(5). The Long Wavelength Infrared
Camera (LWIC) for use in the 8-14µm
spectrum. It uses a 20 x 64 BIB array
from Hughes and, depending on wavelength, the angular resolution is 0.08
to 0.32 arc-seconds.
On November 7th, 1991, the telescope was officially dedicated at a
ceremony at the summit. At this stage,
only nine mirrors were in place but
already the first official observation
and concept-proving run had been
made. The first image obtained was
a CCD image of the galaxy NGC 1232
(Arp 41) in Eridanus.
The results were as encouraging as
the design and construction team had
hoped, fully vindicating the optimism
they had shown in this radical new
telescope. The image showed detail
that had not been previously seen from
ground based telescopes, and was a
portent of what was to come once all
segments were in place and the telescope fully commissioned.
Although the warping harnesses
had not yet been fully adjusted, and
seeing was less than perfect, Airy
disc star images were obtained with
diameters of 0.61 arc-seconds at the
50% energy level, and 80% of the
light fell in a circle 1.6 arc-seconds
AUSTRALIAN MADE TV
TEST EQUIPMENT
12 Months Warranty on Parts & Labour
SHORTED TURNS TESTER
Built-in meter to check EHT transformers including split diode type,
yokes and drive transformers.
$95.00 + $4.00 p&p
HIGH-VOLTAGE PROBE
Built-in meter reads positive or negative
0-50kV. For checking EHT & focus as
well as many other high tension voltages.
$120.00 + $5.00 p&p
GW
QUALITY
SCOPES
100MHz
DEGAUSSING WAND
Great for computer monitors. Strong magnetic
field. Double insulated, momentary switch
operation. Demagnetises colour picture tubes,
colour computer monitors, poker machines
video and audio tapes. 240V AC 2.2 amps,
7700AT. $85.00 + $10.00 p&p
TUNER REPAIRS
From $22. Repair or
exchange plus p&p.
Cheque, Money Order, Visa, Bankcard or Mastercard
TUNERS
PLUS
FREE
DMM
40MHz
216 Canterbury Rd,
Revesby, NSW 2212,
Australia.
Phone for free product list
Phone (02) 774 1154 Fax (02) 774 1154
CEBus AUSTRALIA KITS
CEBus Australia has opened the Circuit Cellar door to bring you a range
of high quality, educational electronics kits. There are three types of kit
available: an Experimenter’s Kit which includes the PCBs, manuals, any
key components that are hard to find and the basic software required
by the finished product. Then there is the Complete Kit which includes
everything above plus the additional components required to complete
the kit. Finally, there is the complete kit with Case & Power Supply.
Regardless of which kit you purchase you get the same high quality
solder masked and silk screened PCB and the same prime grade
components.
Our range of kits includes:
HAL-4 4 Ch, EEG Monitor, Complete kit only ................... $356.00
Experimenter’s Kits:
SmartSpooler, 256K print spooler ..................................... $214.00
IC Tester, Tests 74xx00 family ICs .................................... $233.00
Serial EPROM Programmer, For 27xxx devices ............... $214.00
Ultrasonic Ranger Board with Transducer.......................... $194.00
NB: The above prices DO NOT include sales tax.
Don’t forget we also have the HCS II, Home Control System, available,
Its features include: Expandible Network, Digital & Analog 1/O, X-10
Interface, Trainable IR Interface and Remote Displays.
Call fax or write to us today for more information.
Bankcard, Mastercard & Visa accepted.
CEBus AUSTRALIA.
Ph (03) 467 7194. Fax (03) 467 8422.
PO Box 178, Greensborough, Vic 3087.
ESCORT
EDM-1133
20MHz
•
•
•
•
•
•
3¾ Digits
Autoranging
8 Functions
DC V, AC V
DC A, AC A
Ohms
Valued at
$127!
GOS-6100
GOS643
GOS622
4 Channels
2 Channels
2 Channels
100MHz BW
40MHz BW
20MHz BW
500uV - 5V/DIV
1mV - 5V/DIV
1mV - 5V/DIV
Dual Timebase to 2ns/DIV
Dual Timebase to 2ns/DIV
Timebase to 2ns/DIV
Dual Timebase Trig
Audio Trigger Level Lock
Audio Trigger Level Lock
Variable Hold-Off
Variable Hold-Off
Variable Hold-Off
20kV Accel. Voltage
12kV Accel. Voltage
2.2kV Accel. Voltage
EMONA
INSTRUMENTS
NSW (02) 519 3933
VIC (03) 889 0427
QLD (07) 397 7427
Also available from:
WA (09) 244 2777 SA (08) 362 7548 TAS (003) 31 6533
August 1993 11
Table 3: W. M. Keck Telescope Specifications
Optical Design: Ritchey-Chretien
Primary Mirror
Secondary Mirror (f/25)
Effective aperture
8.2m
Figure
Convex hyperboloid
Maximum diameter
10.95m
Shape
Circular
Light-collecting area
75-76 sq.m
Diameter
0.51m
Limiting magnitude
±28
Radius of curvature
1.82m
Figure
Concave hyperboloid
Distance from primary
16.6m
Number of segments
36
Focus behind primary
4.54m
Radius of curvature
35m
Equivalent focal length
250m (f/25)
Focal ratio
1.75
Gap between segments
3mm
Site
Mauna Kea, HI
Total weight of glass
14.7 tonnes
Longitude
West 155 deg 28 min 3 sec
Position actuators
108 - 3 per segment
Latitude
North 19 deg 49 min 6 sec
Whiffletrees
108 - 3 per segment
Elevation of dome
4150m
Displacement sensors
168 - 6-12 per segment
Dome height
31m
Active-control
0.5 second cycle
Dome width
37m
Setting time after siew
10 seconds
Dome moving weight
635 tonnes
Dome air exchange
5 minute cycle
Observatory
Individual Segments
Number of aspheric types
6
Telescope mounting
Altazimuth
Number of each type
6
Max. telescope height
24.6m
Spares of each type on hand
1
Telescope moving weight
270 tonnes
Focal length tolerance
0.2mm
Project cost
$US94 million
Shape
Hexagonal
Construction time
7 years
Greatest diameter
1.8m
Project headquarters
Kamuela, HI
Thickness
75mm
Glass type
Schott Zerodur
Mean annual temperature
0°C
Mass
400kg
Average wind velocity
25km/h
Clear night per year
250
Environmental
Secondary Mirror (f/15)
Figure
Convex hyperboloid
Average relative humidity
Less than 10%
Shape
Circular
Sub-arc-second seeing
Greater than 50% of time
Diameter
1.45m
Radius of curvature
4.73m
Distance from primary
15.41m
Focus behind primary
2.5m
Equivalent focal length
150m (f/15)
across. These images were obtained
at the prime focus since the secondary
and tertiary mirrors had not yet been
installed. After these test images, the
nine mirror segments, already greater
in light collecting capacity than the
5- metre Hale telescope on Mount
Palomar, were removed for safety so
that work could continue on the as yet
unfinished support structure.
At this same November ceremony,
12 Silicon Chip
the ground was turned for a second,
identical telescope, the Keck II. If all
goes according to schedule, Keck II is
expected to be operational some time
in 1996. In October 1991, the Schott
Glassworks began delivery of the first
of the 42 1.9 metre blanks required for
the Keck II.
Used alone, the second telescope
will double the available observing
time. Just as important, the two tele
scopes, 85 metres apart, can potentially be used as an optical interferometer,
giving a light grasp equal to a single
14.1-metre mirror but with the resolving power of a mirror 85 metres in
diameter. In practice, however, this
theoretical resolving limit is unlikely
to be achieved but confidence has been
expressed that a resolution of better
than 0.01 arc-seconds is feasible. The
light collecting area of the two mir-
An optical technician monitors a diamond-edged circular saw as it cuts a
mirror blank to a hexagon. Thirty six of these hexagonal segments are used
in the Keck mirror & the gaps between them are less than 3mm.
rors will be greater than the world’s
current 10 largest optical telescopes
combined!
By early 1992, when 18 of the segments were in place, the telescope
already ranked as the largest optical
reflector. Work had been slowed
down by a snowstorm in November,
hampering access to the summit and
progress once there, but finally, on
April 14th, 1992, the last of the 36
segments was lowered into position.
Designer Jerry Nelson, project manager Jerry Smith, facilities manager
Ron Laub and Don Hall from CARA
were all present for the final mirror
positioning, the culmination of a 15year dream.
Although the telescope is officially
completed, shake-down engineering
tests, alignment, tracking and ironing
out the bugs inevitable in a project of
this size are continuing before it is
finally commissioned. The same can
be said of the fine tuning required to
optimise the new instruments to the
telescope.
This is expected to take about a year
and will be under the watchful eye of
operations director Peter Gillingham,
recently moved to Mauna Kea from
the Anglo-Australian Observatory at
Coonabarrabran, NSW. Most of the
problems encountered earlier in the
telescope pointing software seem to
have been solved but further work is
required to iron out troubles in the
segment active control computer.
From concept to completion, the
Keck telescope has taken nearly two
decades to come to fruition, during
which time many valuable technological lessons have been learned.
Its commissioning will have lasting
implications for astronomy. New horizons have been opened up to keep
researchers and theoretical astro
physicists occupied for years.
It also comes at a time when new
and exciting data is being returned
from the orbiting Hubble Space Tele
scope. Both telescopes have the same
limiting magnitude of about 28 but
they can work independently or in
concert to push the frontier of knowledge forward an order of magnitude
from anything that has gone before.
Hubble’s great strength is its superb
location; Keck’s is its massive light
collecting power. And Keck does it
at 1/16th the construction and operational costs!
Hard on the heels of the now proven
design concepts comes confirmation
that other telescopes of this kind are
to follow – from the US, Japan and
Europe. This is perhaps the greatest
contribution of its designers, builders
and the telescope itself – the heralding
SC
of a new era.
Acknowledgments
“Sky & Telescope” magazine;
CARA; Caltech; Itek Optical Systems; Summit & facility support
staff - especially Andy Pera
la,
Jerry Smith and Mary Beth Murrill.
August 1993 13
|