This is only a preview of the January 1993 issue of Silicon Chip. You can view 65 of the 104 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Items relevant to "Build A Flea-Power AM Radio Transmitter":
Items relevant to "High-Intensity LED Flasher For Bicycles":
Items relevant to "A 2kW 24VDC To 240VAC Sinewave Inverter; Pt.4":
Articles in this series:
Articles in this series:
|
. 1:....
' ."
'
:
.
,,
,~
The Story Of
Electrical Energy, Pt.22
While Sydney Council generated its own power
from 1904, the Railways & Balmain power
station provided a big share of the load in years
to come~ The privately owned Balmain station
was particularly innovative & continued to run
until 1973.
By BRYAN MAHER
Sydney Council's electricity supply undertaking got off to an au.spicious start in 1904, but' it soon had a
battle on its hands. The first real expansion into suburbia took place in
1910. The councils of Annandale in
the west, Mascot to the south and
Woollahra and Randwick in the east
all agreed to supply electricity to
82
SILICON CHIP
streets, homes and businesses. Long
distance transmission to Long Bay
Gaol prompted the council's first rise
in transmission voltage to 1 lkV and
this was completed in 1911.
So busy was the Council Electricity
Department with suburban extensions
that the work ofreplacing the remaining city gaslights lagged and was still
incomplete in 1913. This prompted
calls for a slowing-down of suburban
work.
In the midst of these delays, the
long-established Redfern Municipality Electric Supply undertaking was
actively pursuing business. But then
came an entirely new challenge. In
1908, a brand new private enterprise,
the Balmain Company, was formed,
with the full title of "The Electric
Light and Power Supply Corporation".
This was no small amateur competitor but was a large, professional engineering organisation, a fierce commercial adversary.
Newtown Council rejected Sydney
City Council's overtures and opted to
buy electricity from Balmain. In quick
succession, Leichhardt, Ashfield and
Petersham municipalities gave the
Left: a classic photo of Ultimo power
station taken in 1915. Six turboalternators are pictured here but the
original 1.9MW Parsons turbine is out
of the picture.
Balmain Company exclusive rights to
electrify their suburbs. At the same
time, the North Shore councils sought
to set up their own power stations.
Sydney Council's dream of a huge
electricity system was in grave danger of being boxed in by competitors!
Fast expansion or extinction seemed the only choices. By 1913 the Redfern Electricity enterprise and the remaining city generating company sold
out to the City Council. But the Balmain Company was to remain in the
picture for years to come.
Tungsten filament lamps
The original incandescent lamps of
Swan and Edison used carbon fibre
filaments operating at bright red heat.
These were very wasteful, giving
mostly heat and little light. The advent of tungsten wire filaments iii 1910
allowed a much higher operating temper::iture, giving more light output per
watt. 8ne candlepower per watt of
electricity was achieved. This was 13
times more efficient than the old carbon filament lamps.
Despite the reduction in electricity
consumption per lamp, the load on
the council power station continued
to increase. By 1914, Pyrmont's output had increased fifteenfold to over
22MW and 10,000 customers.
World War I
The war years created grave problems for the council's electricity undertaking. In June 1914, a new German-made turboalternator of SMW
capacity failed after just three months
service. The A.E.G. turbine suffered
damage to one blade wheel, requiring
replacement parts from Germany but
war broke out before they could be
shipped. Therefore a replacement turbine was ordered from the British
Westinghouse Company and delivery
promised within a year.
In the meantime the spare blades
for the German machine turned up in
Sydney Harbour aboard a Swedish
ship, Sweden being neutral in the conflict. The Westinghouse order was
This was the scene at Ultimo in 1950. A turbine attendant reads the recording
instrument panel and logs the steam pressure, condenser vacuum, cooling water
temperature & bearing oil temperature & pressure. Turbine attendants worked
8-hour shifts and did not leave their machines during this time.
promptly cancelled by agreement. But
the new German turbine blades ran
for only 10 days and again failed, the
rotor blades hitting the stator blades
when on load.
Desperate to keep the system going,
the council engineers took an unusual step. They simply removed the
offending blade wheel and let the turbine run with one less set of blades.
Though 15% less efficient, it worked.
No new generators were installed at
Pyrmont until 1921.
Railways to the rescue
So critical was the power shortage
that in 1916 the City Council asked
the Railway Commissioner to supply
electricity from the Ultimo power station. A 2-year contract was eventually
signed for the supply ofup to 4MW of
power. Initially, a 6.6kV 25Hz cable
was run from the tramway substation
in Jamison Street to the City Council's
substation almost next door at Lang
Park.
To make use of this railway power,
the City Council purchased transformers and two rotary converters from
the USA. These changed the railway's
3-p hase 25Hz AC supply to 480/240V
DC for use in city shops and apartments.
By April 1919 increasing quantities
of 25Hz AC power fro m the railways
power stations was supplied to a new
City Council substation in Castlereagh
Street. The city and suburbs were becoming increasingly dependent on
electricity generated at the Ultimo railway power station.
Indeed, the then minister for local
governm ent preferred th e railway department to supply bulk electricity to
outlying suburban councils, who in
return would reticul ate power to
homes and industries. The reasoning
was logical - tramway current load
occurred mostly in the morning and
evening peak hours. During the day
an d at night, the railway power station at Ultimo was only lightly loaded,
just when domestic and industrial
load was at its peak. Sharing power
seemed sensible.
Steam turbines introduced
Fortunately, when one technology
reaches its limit, it sometimes coincides with the practical realisati on of
the next. This situation occurred in
1904, with steam reciprocating engines reaching their zenith and steam
turbines app earing on the scene.
Because of their much higher speed,
steam turbines coul d produce much
more power at greater efficiency than
their reciprocating counterpart. Also
JANUARY
1993
83
were purchased, designed to run at
50% overload during peak hours. Running at 750 RPM, they were directcoupled to 4-pole 25Hz alternators.
Both were running by 1909, though
one machine had to survive a shipwreck on the way out from England.
Continued demand for both tramway and city power led to a further
5MW turboalternator being installed
in October 1911. This WillanRobinson
turbine was called a "disc and drum"
type, being a combined impulse and
reaction machine. The 4-pole alternator was manufactured by Dick Kerr
and Co.
The installation of these three turboalternator sets more than trebled the
output of the station, from 7MW in
1903 to over 23MW by 1911, making
Ultimo the most powerful electricity
generating station in the southern
hemisphere.
These turboalternators at Ultimo power station were made by Standard
Waygood Ltd & were commissioned in 1923. Each machine produced 2.5MW
3-phase power at 50Hz for signals, lighting and bulk supply.
Taken in 1905, this photo shows the first Parsons turbine installed in Australia,
at the Ultimo power station. It was a great deal smaller but much more
powerful than the huge reciprocating steam engines which preceded it.
because of the higher revolutions, the
alternator produced more megawatts
for a given size machine.
The Parsons works at Newcasth: on
Tyne, England, produced the first
steam turbine used for electricity generation in the southern hemisphere.
This 3000hp (2.24MW) turboalternator set was installed in Ultimo power
station in 1904 and was in service by
9th January, 1905. This unit ran at
84
SILICON CHIP
1500 RPM to drive a 2-pole 25Hz alternator, producing 1.875MW of electricity at 6.6kV. It became the precursor of all future designs in power stations. Never again would engineers
think in terms of reciprocating engines.
The continuing rapid expansion of
Sydney's tramway system led to more
Parsons turboalternator sets being installed at Ultimo. Two 5MW machines
First Sydney Harbour Tunnel
The idea of tunnels under Sydney
Harbour is not new and you may be
surprised to learn that the recently
opened traffic tunnel is not the first
tunnel under the harbour. So fast did
the North Shore tramway system expand between 1902 and the following
decade, that difficulties were soon encountered in keeping enough 6.6kV
submarine cables in service.
The cables originally laid on the
floor of the harbour were of 3-core
construction, each core having 3 7
strands of 16SWG copper. The lead
and jute sheathing was not entirely
successful in preventing the ingress
of sea water and a few cables were
also destroyed by ship's anchors.
Therefore, the Railways Department
dug a cable tunnel under the harbour,
from Longnose Point to Greenwich.
The construction of the tunnel was
commenced from a point near Louisa
Road in Birchgrove, close to Snail's
Bay. Simultaneously, a complementary dig was begun on the north side
of the harbour at Greenwich near
Manns Park. The two digging teams
met in the middle below the harbour.
Leaky tunnel
An expensive construction, this
tunnel was large enough for a few
men to walk abreast and was lined
throughout its length. The walls were
fitted with racks in which rested many
3-phase 6.6kV cables. By this means,
AC high tension supply was provided
for all tramway substations on the
north shore.
The under harbour passage was
electrically lit but electricians who
worked down in the depths found it a
foreboding place. The sound of boats'
propellers in the water above could
be clearly heard as could the shuddering thud of a ship's anchor being
dropped.
Many more 6.6kV cables were laid
in this tunnel between 1924 and 1925
to supply the new 1500V DC substations at St Leonards and Gordon for
the electrification of the north shore
railway.
However, water seepage in the tunnel was always a problem and so it
needed to be continuously pumped
to prevent flooding. Once the Harbour Bridge was opened, the underwater cable crossing· was no longer
needed. Eventually, the Railways Department abandoned the tunnel to the
invading seawater.
50Hz generation at Ultimo
The 25Hz current used by the tramway rotary converters and induction
motors was unsuitable for lighting,
due to the obvious low frequency
flicker. By 1915, the Sydney tramway
system was so complex that electric
lamp signals were necessary. In that
year, a Bellis-Norcom 75kW turboalternator was installed at Ultimo.
This generated a 2.2kV 50Hz 3-phase
supply, coming on line on 15th July
1916. At vital points in the city and
inner suburbs, small transformers reduced this to 120VAC single phase
for lighting signals and waiting sheds.
Further 50Hz generators were
quickly added, one of120kW and two
of ZZ0kW capacity. So fast did the
system grow that by 1921 those four
machines were scrapped, to be replaced by four turboalternators each
of 2.5MW 50Hz rating, including two
units made in Sydney by Standard
Waygood Ltd.
Later, between 1925 and 1928,
White Bay power station had installed
four much larger 50Hz 1 lkV generators, taking over the bulk supply role
to Sydney City Council, municipal
councils and outlying towns. Thus,
high frequency generation at Ultimo
was no longer needed and all four
50Hz machines were removed.
White Bay power station had been
opened by the Railways Department
in 1913, initially as a 25Hz supply
r.
Ultimo power station included an AC/DC substation with five lMW rotary
converters. This converted the 25Hz AC supply to 600V DC for trams in the
Ultimo area.
source. The Standard Waygood works
also turned out larger steam turbines
and alternators for that plant. The No.4
and No.5 turboalternators for White
Bay, both 18.75MWunits, were under
construction during 1925/27.
These machines were designed by
English Electric through their Australian counterpart, Associated General Electric Industries. The heavy
casting and machining was shared
between Standard Waygood Ltd and
Cockatoo Island Dockyard. The alternators were also wound in Sydney.
Both were 6.6kV 25Hz units, the largest low frequency machines ever installed at White Bay.
Independent Balmain
The Electric Light and Power Corporation, an independent private company, secured the franchise to supply
the borough ofBalmain in 1906. Consequently, two small reciprocating
steam engine driven generators were
installed on the eastern bank of Iron
Cove. Operation commenced in 1908,
beginning one of the longest-lived private generating concerns in Australia.
The service area was soon extended
to include Newtown, Petersham, Ashfield and Leichhardt and so the generating system was quickly enlarged to
become the Balmain A power station.
By 1923, Balmain A was a well engineered 10MW system of turboalternators and boiler equipment. Situated
immediately north of the Iron Cove
bridge on Victoria Road, between Terry
Street and the water, the station buildings soon became a well-known landmark.
Later Balmain supplied power as
far afield as the Parramatta, Granville
and Dundas areas, taking over from
an earlier generating station at Parramatta.
Risky shipping
Because Balmain's service area included many industrial and shipping
facilities, continuity of supply during
World War 2 was vital. Coal and coke
were burned, originally supplied by
ship from the Newcastle coal fields.
Throughout the war years of 1942-45,
little colliers such as the William Macarther and Hexham Bank dodged attacks by Japanese submarines.
The technique was for the coal ships
to ply between Newcastle and Sydney so close inshore that enemy submarines were not game to follow. The
smallest of these colliers had such
low freeboard that they were almost
impossible to spot. The view through
an enemy periscope was confused by
the background hills of the shoreline,
preventing a clear silhouette for torpedo aiming at the slow moving col~
liers.
By 1942, Balmain was running turbines rated at 18.75MW, 12MW and
9MW. All of these turbines were
driven by steam at 225psi (1550kPa)
and 3 70°C. The total installed turboalternator capacity was 39. 75MW but
boiler capacity totalled only 27MW.
JANUARY
1993
85
L
" 1J1! I
::i
2
·9
Balmain power station was Australia's largest privately owned electricity
generating station. It began operations in 1906 in the building at extreme left &
progressively expanded to lOOMW capacity. It ceased operation in 1973.
tor. Instead, the secondhand unit was
transferred to one of the railway's
smaller power stations to extend its
service life. The inevitable result was
that Newcastle used mostly secondhand generators, rotary converters and
so on.
From 1928 onwards, Ultimo power
station only had 25Hz alternators. To
provide a standby systeip, a frequency
changer was installed at Ultimo in
1937. This 2MW unit consisted of a
6.6kV 25Hz synchronous motor directly coupled to an 1 lkV 50Hz alternator. A belt-driven DC generator
supplied the rotor fields of both units.
This frequency changer was also
secondhand. It had previously served
to link the 25Hz and 50Hz systems at
Zarra Street power station from 1922
to 1936, until replaced there by a much
larger 7.5MW machine.
The ultimate Ultimo
Clearly more boilers were needed but
the company took an approach new
to Australia for that time.
In a bold step, Balmain installed
the highest pressure boiler then seen
in Australia, generating steam at 1250
psi (8600kPa) and 490°C. The huge
boiler towered 26 metres high, with
the 25-tonne drum of forged chrome
molybdenum steel mounted 16 metres above the firing floor. The first
new 9.375MW turboalternator went
into service in 1946, the first "back
pressure" machine ever installed in
Australia.
This machine received steam at
1250psi from the high-pressure boiler
and exhausted spent steam at 225psi
and a temperature of 370°C. The exhaust steam, the so-called back pressure, was used to drive one or two of
the old turbine sets.
High efficiency
The efficiency of any steam engine
depends on the difference in temperature between inlet and exhaust. In the
multiple turbine scheme, the inlet to
outlet temperature difference is measured right across the high and low
pressure machines. Thus, the efficiency of both machines is quite l\igh.
Taken together, the 9.375MW high
pressure and 18. 750MW low pressure
units generated a total of 25.5MW.
The condensate water from the low
pressure machine condenser was then
pumped back into the high pressure
boiler to be converted to steam.
86
SILICON CHIP
The purpose of the Balmain scheme
was twofold: to increase plant capacity and to improve efficiency by enabling old steam turbines to operate
within a higher temperature steam
cycle. The combined high and low
temperature turbines achieved a 50%
increase in power output using only
8 % more fuel.
Three more 25MW high pressure
turboalternator sets and more boilers
were later installed at Balmain. The
total capacity in 1956 was just over
lO0MW and it continued supplying
electricity until 1973.
Railway alternator swaps
Meanwhile, back at the railway's
power stations, further modernisation
was in progress. Of the four 50Hz
generators running at Ultimo since
1921/23, the two Willan-RobinsonDick Kerr units were scrapped in 1928
but the two Australian-made alternators were reinstalled elsewhere. No.1
went to Zarra Street power station in
Newcastle in November 1925, where
it helped supply that city until 1930.
After that, the turbine was removed
and reinstalled at Lithgow power station.
The No.2 machine became the inaugural generator at the new Lithgow
power station which was opened in
1928. These are examples of the musical chairs played by the Railways
Department. Their philosophy was not
to scrap an old machine when it was
to be replaced by a new, larger genera-
By 1950, Ultimo had reached its
greatest output of 83MW, generated
by just four turboalternators. They occupied the large turbine hall which
had originally been built to house six
huge low-speed vertical reciprocating steam engines and alternators.
These would have generated a total of
only 9MW.
Ultimo was closed by the newly
formed Electricity Commission in
1963 at the same time as trams were
phased out, leaving White Bay to carry
the railways and the bulk supply load.
The 65-year history of Ultimo was
an accurate reflection of the development of electric power generation. At
various stages, Ultimo included nearly
every type and class of electricity generation equipment. And on many occasions, it lead the way in size, capacity and technology. Thus, it is fitting
for this station to now be the Powerhouse Museum. Sadly, little of the
equipment remains today.
Acknowledgements
Grateful thanks to the SRA Archives
and the Trustees of the Sydney Museum of Applied Arts and Sciences
for the photographs used in this article. Acknowledgements also to Don
Godden et al in "Ultimo Power House;
Report on its History and Technology"; also to Victor Poljanski, Arthur
Perry, W. H. Myers, G. F. Anderson, P.
Smythe, P. Tweedie, J. Brearley, Pacific Power and the Public Works Department of NSW.
SC
|