This is only a preview of the June 2010 issue of Silicon Chip. You can view 31 of the 112 pages in the full issue, including the advertisments. For full access, purchase the issue for $10.00 or subscribe for access to the latest issues. Articles in this series:
Items relevant to "Air-Quality Meter For Checking CO & CO₂ Levels":
Items relevant to "Dual-Tracking ±19V Power Supply, Pt.1":
Items relevant to "Build a Digital Insulation Meter":
Articles in this series:
Items relevant to "A Solar-Powered Lighting System, Pt.2":
Purchase a printed copy of this issue for $10.00. |
New design tests up to 1000V, down to 250V
Digital
Insulation Meter
By JIM ROWE
Think all your double-insulated power tools are safe, just because
they are double insulated? As many have found to their ultimate
cost, wear and tear on tools can mean that they become decidedly
unsafe. Here’s a meter that will give you back your peace-of-mind
– on tools and many other electrical and electronic devices.
T
his is actually an improved
version of the Digital Megohm
& Leakage Current Meter we
described in the October 2009 issue
of SILICON CHIP.
Our original design had a distinctly
mixed reception from some of our
readers. It could be summed up as
“OK but ….”
The first “but” was that it would
not deliver the nominal test voltage of
1000V or 500V DC into the minimum
load resistance of one megohm, as
specified in the relevant Australian
Standard, ie, AS/NZS 3760:2003.
78 Silicon Chip
The reason for this drawback was
largely because we had set the internal
current limit too low and partly because the DC-DC converter could not
deliver the current required, even if
the current limiting resistor had been
removed.
Furthermore, some readers pointed
out that the test voltage of 500V DC
was too high for testing insulation of
equipment with EMI suppression and
MOVs (metal oxide varistors). These
devices should be tested at no more
than 250V DC.
Faced with that criticism, all we
could do was to revise the design so
that (a) the inbuilt DC-DC converter
can deliver the full test voltage into
a 1MΩ resistor and (b) provide the
additional test voltage of 250V DC.
In fact, the new circuit can deliver
the test voltage of 250V or 500V into
a load of 100kΩ, if required, for the
testing of portable RCDs (residual current devices).
The physical presentation of the
new meter is also quite similar to
the original except that it now has
a 3-position switch to select the test
voltages of 250V, 500V or 1000V DC.
siliconchip.com.au
Apart from the redesigned
D2
inverter section, the revised
5V
K
A
+5V
meter now has two current
D3
REGULATOR
250V, 500V OR 1000V
K
ranges instead of one, under
A
TEST
T1
the control of a PIC micro(S2)
controller.
4.7k
LCD
9V
As before, the Digital
MODULE
BATTERY
+
Insulation Meter is easy to
TEST
build, with most of the maTERMINALS
–
RD1
jor components mounted
directly on two small PC
IL
'SMART'
ADJUST
AMPLIFIER
Q3
DC/AC INVERTER
DIGITAL
TEST
boards. These fit snugly
A = 3.1
(IC1, Q1, Q2)
VOLTMETER
VOLTAGE
(IC2a)
inside a compact UB1 size
(IC3)
(VR1)
jiffy box, along with a 6xAA
100
+1.25V
battery holder used to supRLY1
+5V
ply the meter’s power.
RD4 1000V
Q4
SELECT
TEST
It can be built up in a
RD2
VOLTAGE
9.90k
AUTO CURRENT
500V
few hours and for an outlay
(S1)
RANGE SWITCHING
RD3
much lower than commer250V
cially available electronic Fig.1: in this block diagram, the two sections of the circuit can be clearly identified. On the
megohm meters.
left is the power supply, consisting of a regulated 5V plus a high-voltage supply. On the right
So to summarise, it can is the metering and display unit. These can be seen in the two separate PC boards below.
now test at 250V, 500V or
1000V and can measure leakage curThe feedback uses a voltage divider
The basic voltage divider using RD1
rents from below 1A to above 6mA.
(RD1 and RD2) to feed a small proporand RD2 alone is used to set the high
As well, it can measure insulation
tion of the high voltage DC output back
voltage level to 250V, with multi-turn
resistance from below 1MΩ up to
to one input of a comparator inside
trimpot VR1. To change the test voltage
999MΩ.
IC1, where it is compared with an
level to 500V or 1000V, switch S1 is
internal 1.25V reference voltage.
used to connect RD3 or RD4 in parallel
How it works
The output of the comparator is
with RD2, increasing the division ratio
The block diagram of Fig.1 shows
then used to control the operation of
of the divider and hence increasing
the arrangement of the new meter with
the DC-DC converter, turning it on
the output voltage maintained by the
its somewhat more complex DC-DC
when the output voltage is below the
feedback loop.
converter. This is on the left-hand side.
correct level and turning it off again
Note that the converter generates
The metering section, on the right
when the output voltage reaches the
the test voltage only when TEST
side of the diagram, is used to measure
correct level.
button switch S2
any leakage current which flows beis pressed and
tween the test
held down. As
terminals and
soon as the
from this it
button is recalculates the
leased, the
external resistance
converter
connected between
stops and
them (knowing the
test voltage in use).
In more detail, the
DC-DC converter converts the 9V DC from the
battery into AC, so it can be
stepped up to a few hundred volts
using an auto-transformer. The resulting high voltage AC is then rectified using ultra-fast diode D3 to produce the
test voltage of 250V, 500V or 1000V DC.
We use negative feedback to control
the converter’s operation and maintain
its output voltage at the correct level.
Inside our Mk II Insulation meter. The
PC board in the bottom of the box is
the high voltage generator; the board
“hanging” from the front panel handles
the metering and display tasks.
siliconchip.com.au
June 2010 79
D2
POWER
A
REG1 7805
K
S3
TEST 470 F
16V
S2
9V
BATTERY
+5.0V
OUT
IN
GND
100nF
D3
+9V
(NOM)
T1
0.1
5W
6
3
+HV
K
A
3.3M
#
120T
7
Ips
11T
8
DrC
SwC
Vcc
IC1
MC34063
SwE
Ct
GND
4
1
B
2
C
Q1
BC337
E
100
E
Cin5
B
2.2k
1nF
3.3M
#
Q3
IRF540N
G
4.7k
1W
3.3M
#
D
3.3M
#
S
Q2
BC327
100nF
630V
10M
#
120k
C
SET
VOLTS
+1.25V
+
TEST
100nF
TERMINALS
630V
–
10M
#
VR1
1M
(25T)
# HV TYPES
(1.6kV RATING)
Vfb
(HV DC-DC
CONVERTER
BOARD)
22k
TP3
680
1000V
68k
1nF
68k
TPG
500V
100nF
S1a
GND
250V
SC
2010
SELECT
TEST VOLTS
DIGITAL INSULATION METER
Fig.2: the circuit is based on a PIC16F88 microprocessor which measures the current between the test terminals (and
therefore the device under test). The high voltage DC-DC converter supplies up to 1000V for these tests in accordance
with the relevant Australian/New Zealand standards. It can also supply lower voltages (250 and 500V) as required.
the high voltage leaks away via RD1 and RD2/RD3/RD4.
This is both a safety feature and a simple way to achieve
maximum battery life.
Referring back to Fig.1, the meter section uses a shunt
resistor connected between the negative test terminal and
ground to sense any leakage current IL which may flow
between the test terminals. It is the voltage across this resistor which we measure, to determine the leakage current.
The effective shunt resistance is switched between 100Ω
and 10kΩ to give the meter two measurement ranges. The
switching is done using relay RLY1, under the control of
the PIC microcontroller (IC3) inside the metering circuit.
Initially the shunt has a value of 100Ω, which means that
a leakage current of 10mA produces a voltage drop of 1.00V.
This provides the ‘high current’ measuring range. If and when
the measured leakage current falls below 100A, RLY1 is
turned off to increase the effective shunt resistance to 10kΩ.
This provides the ‘low current’ measuring range, where a
leakage current of 100A produces a voltage drop of 1.00V.
If this shunt resistance relay switching looks familiar,
that’s because we used a similar arrangement in the Capacitor Leakage Meter published in the December 2009
issue and in the Capacitor Leakage Adaptor for DMMs in
the April 2010 issue.
The voltage drop across the shunt resistance is fed
80 Silicon Chip
through op amp IC2a which has a voltage gain of 3.1 times.
IC2a drives IC3, a PIC16F88 microcontroller which is used
as a ‘smart’ digital voltmeter.
The amplified voltage from IC2a is fed to one input of the
ADC (analog to digital converter) module inside IC3, where
it is compared with a reference voltage of 3.2V. The digital
output of the ADC is then mathematically scaled, to calculate
the level of the leakage current in milliamps or microamps.
IC3 is then able to use this calculated current level to
work out the insulation resistance, because it can sense the
position of switch S1 and hence ‘knows’ whether the test
voltage being used is 250V, 500V or 1000V.
So all it has to do is calculate the total resistance which
will draw that level of leakage current from the known
test voltage, and then subtract the ‘internal’ 4.7kΩ and
100Ω/10kΩ resistors from this total value to find the external resistance between the test terminals. The calculated
leakage current and insulation resistance values are then
displayed on the LCD, along with the test voltage being used.
In case you’re wondering about the purpose of the 4.7kΩ
resistor connected between the high voltage generation
circuit and the positive test terminal (ie, inside the meter),
it’s mainly to limit the maximum current that can be drawn
from the DC-DC converter – even in the event of a short
circuit between the test terminals.
siliconchip.com.au
+5.0V
2.2k
10k
Q4
BC327
E
220 F
3.3k
4
14
Vdd MCLR
2.2k
B
100nF
18
Vref+
RA1
+3.2V
2
C
5.6k
TP1
1.5k
10k
250V
S1b
10k
TPG
500V
17
1000V
16
A
13
ZD2
5.1V
100nF
1k
3
2
100
1M
6
K
ZD1
6.2V
1W
D1
10k
IC2a
K
RB3
1
4
10
6
RS
D7 D6 D5 D4 D3 D2 D1 D0 GND
1
14 13 12 11 10 9 8 7
9
180
CLKo
A
15
Vss
5
1.8k
A
K
This should make the meter relatively safe to use, especially as it won’t be too easy to connect yourself between
the two test terminals while simultaneously holding down
the Test button.
Of course, if you’re really determined to give yourself a
shock it can be done . . . but we wouldn’t recommend it!
Incidentally, if you do deliberately short circuit the
output terminals while pressing the test switch (S2), you
will burn out the 4.7kΩ 1W current-limiting resistor; it
can be regarded as a fusible resistor. You will then have to
replace the resistor but at least the rest of the circuit will
have been protected.
If you suspect that you have blown the 4.7kΩ resistor
by shorting the output, test the output voltage of the unit
with your DMM on a high DCV range. If there is voltage,
it’s still working!
Circuit details
Now let’s look at the full circuit diagram of Fig.2.
The DC-DC converter is based on IC1, an MC34063
converter/controller which drives MOSFET Q3 via driver
transistors Q1 and Q2. When the inverter is operating, the
transistors switch Q3 on for a brief time (about 50s) which
allows current to flow from the +9V supply through the
primary winding of transformer T1.
siliconchip.com.au
R/W
5
8
7
RB1
6
RB0
AN2
B-L K
16
IC2: LM358
5
TP2 (2.0MHz)
6
IC2b
7
4
TPG
LM7805
D
BC327, BC337
D1, D2: 1N4004
D3: UF4007
K
3
EN
IRF540N
A
CONTRAST
RB2
2
ZD1
15
B-L A
16 x 2 LCD MODULE
RB4
RB6
11
2
Vdd
A = 3.10
A
7,8
RB5
IC3
RB7 PIC16F88
8
1
LCD
CONTRAST
RA0
3.6k
RLY1
1,14
12
VR2
10k
22
270
RA7
3 RA4
K
+5.0V
B
E
C
GND
IN
G
D
S
GND
OUT
As a result, energy is stored in T1’s magnetic field.
Then Q3 is switched off again, causing the magnetic field
to collapse. This causes a high ‘back-EMF’ voltage to be
generated in both windings of T1, which are connected in
auto-transformer fashion, so that the total voltage applied to
the anode of diode D3 is equal to the sum of the back-EMF
in both windings plus the 9V supply voltage.
D3 then conducts to charge up the series-connected
100nF/630V capacitors to this high voltage. Both of these
capacitors have a 1.6kV-rated 10MΩ shunt resistor included
to ensure that the converter’s high output voltage is shared
equally between them. This is only important when the test
voltage setting is 1000V – we want to ensure that neither
capacitor has its 630V rating exceeded.
The four 3.3MΩ high-voltage resistors, together with the
120kΩ resistor and trimpot VR1, correspond to the upper
divider resistor RD1 in Fig.1. The 68kΩ resistor connected
between pin 5 of IC1 and ground corresponds to RD2, the
fixed lower leg of the feedback divider which provides the
converter’s 250V output voltage. The other 68kΩ resistor
switched by S1a corresponds to RD3, while the 22kΩ and
680Ω resistors connected in series correspond to RD4.
Providing S2 is on, the converter will continue to run
until the high voltage output reaches the correct level. That’s
because until this level is reached, the proportion of the
June 2010 81
Z-7013 (B/L)
16X2 LCD MODULE
ALTRONICS
& M H O GE M LATI GID
RETE M E GAKAEL N OITALUS NI
LCD
CONT
10150140
100nF
IC2
LM358
1.8k
+HV
FROM
DC/DC
CONV
6.2V
5.6k
ZD1
3.3k
4.7k 1W
V++
3.2V
ZD2
TP1 TPG
Q4
BC327
REG1
LM7805
1
10k
10k
220 F
1k
100
2.2k
2
D1
3
S1
1M
2.2k
10k
RLY1
TPG
TEST
TERMINALS
5.1V
4004
1
22k
68k
POWER
3
4004
+
D2
680
2
1
SELECT
TEST VOLTS
–
1.5k
+9V
470 F
GND Vfb
S2
S3
V--
100nF
IC3
PIC16F88
2MHz
3.6k
180
270
22
1
100nF
100nF
TP2
0102 ©
14 13 12 11 10 9 8 7 6 5 4 3 2 1 16 15
10k
VR2
10k
TEST
9V BATTERY
ALL LEADS RUN
UNDER MAIN BOARD
3.3M
3.3M
100nF
630V
Q1
IC1
34063
Q2
1nF TPG
1.25V
0102 ©
68k
TP3
20150140
0.1 5W
VR1
1M
ADJUST HV
CDT1
- CD V H
RETREV N O C
2.2k
1nF
100nF
630V
S
100
UF
4007
Q3
IRF540N
T
F
3.3M
10M
D3
10M
3.3M
120k
+HV OUT
CONVERTER BOARD
Vfb
GND
+9V
Fig.3: component layouts for both the main (measurement/display) PC board (top) and the high voltage DC-DC converter
PC board (bottom), along with matching photographs alongside. Follow these diagrams exactly, not only to ensure your
unit works perfectly but also to minimise the risk of you getting a bite. (It probably won’t do any damage but why risk it!)
output voltage fed back to the comparator input (pin 5) of
IC1 will not reach the +1.25V reference level inside IC1.
However as soon as the high voltage output does reach the
correct level, the proportion fed back to pin 5 will rise just
above 1.25V and IC1 will stop turning Q3 on – stopping
the converter even if S2 is still being held down.
The converter gets its power directly from power switch
S3 (via S2 and D2), so it is supplied with the full battery
voltage less the drop in D2. All of the remaining circuitry in
the meter operates from a regulated +5V supply line, derived
from the battery via REG1, an LM7805 3-terminal regulator.
Smart metering
The metering side of the circuit is fairly straightforward,
thanks to the use of a PIC16F88 micro (IC3). As noted before,
82 Silicon Chip
the signal from op amp IC2a is fed to pin 1 of IC3, which
is configured as ADC input channel AN2 and the microcontroller then makes its calculations to drive the LCD.
Once it has measured and calculated the leakage current in this way, the micro can then calculate the effective
leakage resistance. This is because it is able to sense the
position of test voltage selector switch S1, via the contacts
of S1b which are connected to input pins 17 (RA0) and 16
(RA7). So knowing the test voltage in use it can calculate
the total resistance connected between the test terminals.
Then finally it works out the external resistance between
the terminals by subtracting the 4.8kΩ or 14.7kΩ internal
resistance.
Both of the calculated current and resistance values are
then displayed on the LCD module, along with the test
siliconchip.com.au
Winding the transformer
Step-up autotransformer T1 has a primary winding
comprising 11 turns of 0.7mm enamelled copper wire
(one layer), followed by a secondary winding of 120 turns
(4 x 30-turn layers) of 0.25mm enamelled copper wire.
As shown in the assembly diagram at right, all five layers
are wound on a small Nylon bobbin which fits inside a
two-piece ferrite pot core measuring 26mm in diameter.
First wind on the 11-turn primary using the 0.7mm diameter wire. You’ll find that this will neatly take up the full
width of the bobbin providing you wind the turns closely and
evenly. Then cover this first layer with a 9mm-wide strip of
plastic insulating tape or thin ‘gaffer’ tape, to hold it down.
Leave about 50mm of wire free of the bobbin at the ‘start’
end, and cut any surplus wire off about 40mm from the
‘finish/tap’ end (taking it out via one of the ‘slots’).
Next take one end of the 0.25mm wire and twist it around
the ‘finish/tap’ end of the primary winding to anchor it while
you wind the first layer of the secondary. This must be
wound on the bobbin in the same direction as the primary,
as if it is a continuation of the first layer. If you wind them
closely and evenly you should find that you will be able to
fit 30 turns across the bobbin.
Once you have wound on the 30 turns, cover this second
layer (the first secondary layer) with a 9mm-wide strip of
plastic insulating tape to hold it in place. Then you can
wind the third layer in exactly the same way, covering it
with a strip of tape as before.
The remaining wire can then be used to wind the two
further 30-turn layers, again making sure that you wind
them in the same direction as you wound the earlier layers
and covering each layer with a strip of tape.
With fifth and final layer been wound and taped, the ‘finish’ end of the wire can then be brought out of the bobbin
via one of the slots (on the same side as the start and
tap leads), and your wound transformer bobbin should
be ready to fit inside the two halves of the ferrite pot core.
Just before you fit the bobbin inside the bottom half
of the pot core, though, there’s a small plastic washer to
prepare. This is to provide a thin magnetic ‘gap’ in the pot
core when it’s assembled, to prevent the pot-core from
saturating (magnetically) when it’s operating.
The washer is very easy to cut from a piece of the thin
clear plastic that’s used for packaging electronic components, like resistors and capacitors. This plastic is very
close to 0.06mm thick, which is just what we need here.
So the idea is to punch a 3-4mm diameter hole in a piece
of this plastic using a leather punch (or something similar
to cut a clean hole) and then use a small pair of scissors
to cut around the hole in a circle, with a diameter of 10mm.
Your ‘gap’ washer will then be ready to place inside the
lower half of the pot core, over the centre hole.
Once the gap washer is in position, you can lower the
wound bobbin into the pot core around it, and then fit the
top half of the pot core. The autotransformer should now
be ready for mounting on the converter PC board. To begin
this step, place a Nylon flat washer on the 25mm-long M3
Nylon screw that will be used to hold it down on the board.
Then pass the screw up through the 3mm hole in the PC
siliconchip.com.au
UPPER SECTION
OF FERRITE
POT CORE
BOBBIN WITH
WINDING
(11T OF 0.7mm DIA
ENAMELLED COPPER
WIRE FIRST (END IS TAP),
FOLLOWED BY 4 x 30T LAYERS
OF 0.25mm DIA
ENAMELLED COPPER WIRE
WITH INSULATING TAPE
BETWEEN LAYERS)
FINISH
TAP
START
'GAP' WASHER OF 0.06mm
PLASTIC FILM
LOWER SECTION
OF FERRITE
POT CORE
(ASSEMBLY HELD TOGETHER & SECURED TO CONVERTER
PC BOARD USING 25mm x M3 NYLON SCREW & NUT)
board corresponding to the centre of the transformer, and
lower the assembled pot core down over the Nylon screw,
holding it together with your fingers (with the bobbin and
gap washer inside) and with the ‘leads’ towards diode D3.
Then when the pot-core assembly is resting on the
top of the converter board, keep holding it and the board
together with the Nylon screw together so you can apply
the second M3 Nylon flat washer and M3 nut to the upper
end of the screw. Tighten the nut so that the pot core is
not only held together but also secured to the top of the
PC board.
Once this has been done, all that remains as far as
the transformer is concerned is to cut the start, tap and
finish leads to a suitable length, scrape the enamel off
their ends so they can be tinned, and then pass the ends
down through their matching holes in the board so they
can be soldered to the appropriate pads.
Make especially sure that you scrape, tin and solder
BOTH wires which form the ‘tap’ lead – ie, the finish of the
primary winding and the start of the secondary. If this isn’t
done, the transformer won’t produce any output.
It’s also a good idea to fit a 25mm length of insulating sleeving over the exposed ‘finish’ lead, between the
transformer winding and the PC board. This will help
prevent any ‘flashover’ when the transformer is producing
1000V pulses.
June 2010 83
PARTS LIST – DIGITAL INSULATION METER
1 UB1 size jiffy box, 157 x 95 x 53mm
1 PC board, code 04106101, 109 x 84mm
1 PC board, code 04106102, 70 x 51mm
1 LCD module, 2 lines x 16 characters with LED back-lighting
(Altronics Z-7013, Jaycar QP-5512 or equivalent)
1 Ferrite pot core pair, 26mm OD, with bobbin to suit
1 500mm length of 0.7mm diameter enamelled copper wire
1 8m length of 0.25mm diameter enamelled copper wire
1 100mm length 0.7mm diameter tinned copper wire
1 10x AA battery holder (flat), cut down to 6x
1 2-pole rotary switch, PC board mounting, with 16mm knob (S1)
1 SPST pushbutton switch, panel mounting (S2)
1 SPDT mini toggle switch, panel mounting (S3)
1 Mini DIL reed relay, SPST with 5V coil
2 Binding post/banana jacks (1 red, 1 black)
2 4mm solder lugs
1 16-pin length of SIL socket strip
1 16-pin length of SIL pin strip
1 18-pin IC socket
2 8-pin IC sockets
4 25mm M3 tapped metal spacers
2 12mm M3 tapped Nylon spacers
11 6mm M3 machine screws, pan head
4 6mm M3 machine screws, csk head
3 M3 hex nuts, metal
4 12mm M3 machine screws, Nylon
1 25mm M3 machine screw, Nylon
9 M3 hex nuts, Nylon
6 M3 flat washers, Nylon
12 1mm diameter PC board terminal pins
Semiconductors
1 MC34063A converter controller (IC1)
1 LM358 dual op amp (IC2)
1 PIC16F88 microcontroller, programmed with 0410610A.hex (IC3)
1 LM7805 5V regulator (REG1)
1 BC337 NPN transistor (Q1)
2 BC327 PNP transistor (Q2,Q4)
1 IRF540N 100V N-channel Mosfet (Q3)
1 6.2V 1W zener diode (ZD1)
1 5.1V 1W zener diode (ZD2)
2 1N4004 1A diode (D1,D2)
1 UF4007 ultra-fast 1000V diode (D3)
Capacitors
1 470F 16V RB electrolytic
1 220F 10V RB electrolytic
2 100nF 630V metallised polyester
2 100nF 100V MKT metallised polyester
2 100nF multilayer monolithic ceramic
2 1nF 100V MKT metallised polyester
Resistors (0.5W 1% metal film unless specified)
2 10MΩ HV*
4 3.3MΩ HV*
1 1MΩ
1 120kΩ
2 68kΩ
1 22kΩ
4 10kΩ
1 5.6kΩ
1 4.7kΩ1W
1 3.6kΩ
1 3.3kΩ
3 2.2kΩ
1 1.8kΩ
1 1.5kΩ
1 1kΩ
1 680Ω
1 270Ω
1 180Ω
2 100Ω
1 22Ω
1 0.1Ω 5W wirewound
1 1MΩ mini 25T vertical trimpot (VR1)
1 10kΩ mini horizontal trimpot (VR2)
84 Silicon Chip
* HV (1.6kV rated)
e.g, MH25 series
Farnell 110-0295
(10MΩ) and Farnell
110-0288 (3.3MΩ)
voltage being used.
IC3 is using its internal clock oscillator, running at very close to 8MHz.
This gives an instruction cycle time
of 2MHz, which may be monitored
using a scope or frequency counter at
test point TP2.
Trimpot VR2 allows the LCD
module’s contrast to be adjusted for
optimum visibility, while the 22Ω
resistor connected to pin 15 sets the
current level for the module’s inbuilt
LED back-lighting. This was chosen for
the best compromise between display
brightness and battery life, as the LED
back-lighting is a major component of
total battery current.
Construction
As you can see from the photos and
diagrams, most of the components
used in the new meter are mounted
directly on two small PC boards.
The high voltage converter circuitry
all mounts on the smaller of the two
boards, which measures 70 x 51mm
and is coded 04106102. This board sits
in the bottom of the UB1 box, at the
front of the 6xAA cell battery holder.
Most of the remaining components
mount on the larger board, which
measures 109 x 94mm and is coded
04106101. This board attaches to the
underside of the box lid/front panel via
four 25mm long M3 tapped spacers.
The only components not mounted
on either board are the test terminals,
pushbutton switch S2 and power
switch S3; these all mount directly on
the lid/front panel.
The location of all of the components mounted on both boards, along
with their correct orientation, should
be clear from the overlay diagram of
Fig.3.
There are only two wire links to be
fitted to each board, so these are best
soldered first so they won’t be forgotten. After both pairs of links are in
place you can fit the terminal pins on
the larger board, for test points TP1 and
TP2 and their reference grounds plus
those for the 9V battery connections
(at lower left) and the three at lower
right for the interconnections to the
converter board.
There are a further six terminal pins
to fit on the smaller board: for TP3 and
its ground, the three interconnection
wires to the larger board (at lower
right) and finally for the high voltage
output (upper left).
Once the terminal pins have been
siliconchip.com.au
NEGATIVE TEST TERMINAL
POSITIVE
TEST
TERMINAL
(S3
BEHIND)
MAIN BOARD MOUNTED
BEHIND LID USING
4 x 25mm M3 TAPPED SPACERS
LCD MODULE MOUNTED ABOVE
MAIN BOARD USING 2 x 12mm
LONG M3 TAPPED NYLON SPACERS
16-WAY SIL
PIN STRIP
S1
S2
S1
16-WAY
SIL SOCKET
RLY1
104K
630V
T1 POTCORE HELD TO
CONVERTER PC BOARD USING
25mm x M3 NYLON SCREW
WITH NUT & FLAT WASHERS
CONVERTER PC BOARD MOUNTED
IN BOTTOM OF BOX USING 4 x 12mm
M3 NYLON SCREWS WITH 4 x FLAT
WASHERS & 8 x NYLON M3 NUTS
6xAA CELL HOLDER (CUT DOWN FROM 10xAA HOLDER)
MOUNTED IN BOTTOM OF BOX USING DOUBLE-SIDED TAPE
Fig.4 (at top): an
“X-ray” diagram, through the
side of the case, to show how it
all goes together. The matching
photo underneath is of the main
PC board and panel removed
from the case..
fitted you can fit the sockets for IC1
(on the smaller converter board), IC2
and IC3.
Next come all of the fixed resistors, taking particular care to fit each
value in its correct position. Follow
these with the two trimpots, making
sure you fit these with the orientation
shown in Fig.3.
The capacitors are next, starting
with the lower value ceramic and metallised polyester caps and following
these with the 1nF (on the converter
board) and the two polarised electrolytics on the main board – again matching their orientation to that shown in
Fig.3. The 100nF 630V polyester caps
can be fitted also at this stage.
After the capacitors you can fit
diodes D1 and D2 on the main board
and D3 on the converter board, taking
care to orientate them as shown in
Fig.3 and also to fit the UF4007 diode
as D3. These diodes can then be followed by zener diodes ZD1 and ZD2,
siliconchip.com.au
which both go just above the centre
of the main board. Note that these are
orientated in opposite ways as shown
in Fig.3, and also that the 6.2V zener
is ZD1 while the 5.1V zener is ZD2.
Now you can solder transistors Q1
and Q2 to the converter board, making sure that you fit the BC337 device
as Q1. You can also fit the remaining
BC327 transistor (Q4) on to the main
board.
After the transistors you can fit reed
relay RLY1, making sure you orientate
it with the ‘notch’ end uppermost as
indicated in Fig.3. Then comes the
rotary switch (S1), after first cutting
its spindle to a length of about 15mm
from the threaded mounting sleeve
and filing off any burrs.
Mount the switch in the board so
that it is orientated with the locating
spigot in the ‘5 o’clock’ position, and
push the switch pins through the board
holes as far as they’ll go before soldering to the pads underneath.
Once the switch is fitted, you should
remove its main nut/lockwasher/position stopwasher combination and turn
the spindle by hand to make sure it’s
at the fully anticlockwise limit. Then
refit the position stopwasher, making
sure that its stop pin goes down into
the hole between the moulded ‘3’ and
‘4’ digits.
After this refit the lockwasher and
nut to hold it down securely, allowing
you to check that the switch is now
‘programmed’ for the correct three positions – simply by clicking it around
through them by hand.
Next fit the LM7805 regulator (REG1)
on the main board. This is in a TO-220
package and mounts flat against the
top of the board, with its leads bent
down by 90° about 6mm from the case
so they pass down through the board
holes. The regulator is then attached to
the board using a 6mm long M3 screw
and nut, passing through the hole in
its tab. The screw and nut should be
June 2010 85
tightened to secure the regulator in
position before its leads are soldered
to the pads underneath.
Mosfet Q3 is also in a TO-220 package and is mounted on the smaller converter board in exactly the same way.
The final component to be mounted
directly on the main board is the
16-way length of SIL (single in-line)
socket strip used for the ‘socket’ for the
LCD module connections. Once this
has been fitted and its pins soldered to
the pads underneath, you’ll be almost
ready to mount the LCD module itself.
However, before this can be done
fasten two 12mm long M3 tapped nylon spacers to the board in the module
mounting positions (one at each end)
using a 6mm M3 screw passing up
through the board from underneath
and then ‘plug’ a 16-way length of SIL
pin strip into the socket strip you have
just fitted to the board. Make sure the
longer ends of the pin strip pins are
mating with the socket, leaving the
shorter ends uppermost to mate with
the holes in the LCD module.
Next remove the LCD module from
its protective bag, taking care to hold
it between the two ends so you don’t
touch the board copper. Then lower it
carefully onto the main board so the
holes along its lower front edge mate
with the pins of the pin strip, allowing
the module to rest on the tops of the
two 12mm long nylon spacers.
Then you can fit another 6mm M3
screw to each end of the module, passing through the slots in the module
and mating with the spacers. When
the screws are tightened (but not over
tightened!) the module should be securely mounted in position.
The final step is then to use a finetipped soldering iron to carefully
solder each of the 16 pins of the pin
strip to the pads on the module, to
complete its connections.
The final component to mount on
the converter board is step-up transformer T1, which needs to be wound
first. This may sound daunting, but
there are only 131 turns of wire in all.
You’ll find all of the information on
winding the transformer and mounting it on the converter board in the
box panel.
After this is done you can plug the
three ICs into their respective sockets IC1 on the converter board and IC2 and
IC3 on the main board – making sure
to orientate them all as shown in Fig.3.
At this stage both of your PC board
86 Silicon Chip
17
20
A
39
A
15
53 x 17mm
LCD CUTOUT
B
17
53
37
20
C
HOLE B:
3.5mm DIA
38
HOLES C:
9.0mm DIA
25.5
103
HOLES A:
3mm DIAM,
C
HOLES D:
7.0mm DIA
HOLE E:
12mm DIA
19
D
E
7.5
D
28
A
28
39
A
39
CL
assemblies should be nearly complete.
All that remains is to attach one of the
25mm long mounting spacers to the
top of the main board in each corner,
using 6mm long M3 screws. Then the
board assemblies can be placed aside
while you prepare the case and its lid.
Preparing the case
There are only four holes to be
drilled in the lower part of the case,
to take the mounting screws for the
converter board. These should be
3mm in diameter and with their centres marked out using the converter
board itself as a ‘template’, by sitting
it temporarily inside the box spaced
only about 1mm from the front.
Once these four holes are drilled
and de-burred, you can mount the
Fig.5:
drilling
diagram
for the
UB-1 box
lid, which
becomes
the front
panel. All
dimensions
are in mm.
ALL DIMENSIONS IN MILLIMETRES
converter board inside the box using
four 12mm long M3 Nylon screws,
with a Nylon flat washer and Nylon
nut fitted to each screw first to act as
board mounting pillars or ‘standoffs’.
Then the board can be slipped down
over the screws, and another M3 Nylon
nut placed on each screw to hold the
board in place.
You don’t need mounting holes for
the battery holder, because it can be
held securely in place using two strips
of ‘industrial’ double-sided adhesive
foam tape. However before it can be
fitted into the case it must be cut down
to accommodate only six cells.
This involves cutting off the last
four cell positions altogether (at the
‘negative lead’ end), and then drilling a
2.5mm hole in the end of the sixth cell
siliconchip.com.au
Insulation Testing
LCD
CONTRAST
SILICON
CHIP
+
CAUTION:
HIGH
VOLTAGE!
250
500
–
1000
POWER
TEST
SELECT TEST
VOLTAGE
Digital Insulation Meter
position, at the negative spring end.
The end of the spring is then carefully
bent inwards and around in a circle,
so that it can be held in place using a
6mm long M3 machine screw and nut,
which will also attach the negative
lead connection lug on the outside.
The converted battery holder can
now be fitted inside the main section
of the box behind the converter board,
with the connection lead side to the
left. Mount it using double-sided
adhesive foam as mentioned earlier.
The box lid needs several holes
drilled, plus a rectangular cutout
near the upper end for the LCD. The
location and dimensions of all these
holes are shown in Fig.5, which can
also be used (or a photocopy of it) as
a drilling template. The 12mm hole
siliconchip.com.au
Fig.5: samesize front
panel artwork
which can be
photocopied
and glued to
the panel. For
protection, it
should first be
laminated or
sealed with
self-adhesive
clear plastic.
for S2 and the 9mm holes for the test
terminals are easily made by drilling
them first with a 7mm twist drill and
then enlarging them to size carefully
using a tapered reamer.
The easiest way to make the rectangular LCD window is to drill a series
of closely-spaced 3mm holes around
just inside the hole outline and then
cut between the holes using a sharp
chisel or hobby knife. Then the sides
of the hole can be smoothed using
small needle files.
We have prepared an artwork for
the front panel which be either photocopied from the magazine (Fig.5)
or downloaded as a PDF file from our
website and then printed out. The
resulting copy can be attached to the
front of the lid and then covered with
Testing the insulation of mainspowered equipment and cables is
an important step in ensuring that
they are safe to use and don’t pose
a shock hazard.
According to the Australian and
New Zealand standards for safety
inspection and testing of electrical
equipment (AS/NZS 3760:2003),
tests on the insulation of ‘domestic’
cables and equipment operating
from 230V AC should be carried out
with a testing voltage of 500V DC.
However where the equipment
includes MOV surge protection
devices, the testing can be carried
out with a voltage of 250V DC.
The recommended testing voltage for insulation tests on industrial
equipment such as ovens, motors
and power converters operating
from three-phase 400V AC is
1000V DC.
Insulation tests on domestic
230V equipment can be performed
by measuring either the leakage
current or the insulation resistance.
For Class I (earthed) equipment
with accessible earthed metal
parts, the leakage current should
be no greater than 5mA, except
for portable RCDs (residual current
devices) where it should not be
greater than 2.5mA. The insulation
resistance for these devices should
be not less than 1MΩ or not less
than 100kΩ for a portable RCD.
For Class II (double insulated)
equipment, the insulation resistance with the power switch ‘on’
measured between the live supply
conductors (connected together)
and external unearthed metal
parts should again be not less
than 1MΩ.
The same insulation resistance
figure of 1MΩ applies to extension
cables and power boards (between
the live conductors and the earth
conductor), to power packs (between the live input pins and both
output connections), portable isolation transformers (between the primary winding and external earthed
or unearthed metal parts, between
primary and secondary windings,
and also between the secondary
winding and external earthed or
unearthed metal parts).
June 2010 87
The three LCD screens which should greet you when you turn the Digital Insulation Tester on. The one on the left is self
explanatory. It changes automatically to the middle one, which tells you what to do (it’s not rocket science). The right
screen shows the test voltage (as set by S1), the leakage current (in this case zero – bewdy!) and the measured resistance.
self-adhesive clear film for protection
against finger grease, etc.
(A more robust alternative is to hotlaminate the paper panel in a clear
pouch, cut it to size and then attach it
using thin double-sided tape.)
You might also like to attach a 60
x 30mm rectangle of 1-2mm thick
clear plastic behind the LCD viewing
window, to protect the LCD from dirt
and physical damage. The ‘window
pane’ can be attached to the rear of
the lid using either adhesive tape or
epoxy cement.
Once your lid/front panel is finished, you can mount switches S2 and
S3 on it using the nuts and washers
supplied with them. These can be
followed by the binding posts used
as the meter’s test terminals. Tighten
the binding post mounting nuts quite
firmly, to make sure that they don’t
come loose with use. Then use each
post’s second nut to attach a 4mm
solder lug, together with a 4mm lockwasher to make sure these don’t work
loose either.
Now you can turn the lid assembly
over and solder ‘extension wires’ to the
connection lugs of the three switches,
and also to the solder lugs fitted to the
rear of the binding posts. These wires
should all be about 30mm long and
cut from tinned copper wire (about
0.7mm diameter).
Once all of the wires are attached,
they should be dressed vertical to the
lid/panel so they’ll mate with the corresponding holes in the main PC board
when the two are combined.
You should now be ready for the
only slightly fiddly part of the assembly operation: attaching the main PC
board assembly to the rear of the lid/
front panel.
This is only fiddly because you
have to line up the extension wires
from switches S2, S3 and the two test
terminals with their matching holes in
the PC board, as you bring the lid and
board together. This is not too difficult
though, so just take your time and the
lid will soon be resting on the tops of
the board mounting spacers. Then you
can secure the two together using four
6mm long machine screws.
Then it’s a matter of turning the
complete assembly over and soldering each of the switch and terminal
extension wires to their board pads.
Once they are all soldered you can clip
off the excess wire with side-cutters.
The final assembly step is fitting the
four wires used to make the interconnections between the two PC boards,
and also soldering the ends of the
battery holder leads to the terminal
pins on the lower end of the main
board. The interconnecting
lead connections are shown
clearly in Fig.3, but there
are two points which
should be stressed. One
is that while light-duty insulated hookup
wire (even rain-
bow cable, which we used) is fine for
the three low voltage leads (+9V, GND
and Vb), you’ll need to use wire with
mains-rated insulation for the high
voltage lead.
The second point is that although
this is not shown in Fig.3 for clarity,
all four of the interconnecting leads
are run underneath the main board,
and connect to it on the copper side.
Note too that although the high voltage lead connects to a terminal pin on
the converter board, it solders directly
to the board copper at the main board
end. A terminal pin can’t be used here,
because it would protrude down too
far when everything is assembled (and
risk flashover to one of the cells in the
battery holder).
Once the interconnecting leads and
battery leads have been fitted, your
new Digital Insulation Meter is almost
ready for its initial checkout. All that
remains is to make sure S3 is in the
Off position and then fit six AA-size
alkaline (or lithium) cells into the
battery holder.
Initial checkout
When you turn power switch
Another view
of the completed
PC boards, ready for
installation in the case. The
smaller board (above) is actually
an early prototype – there are a few differences
in the final version (shown in the overlay).
88 Silicon Chip
siliconchip.com.au
What the PIC firmware does . . .
When power is turned on via S3, the PIC firmware ‘starts
work’ by turning on RLY1 via Q4, to ensure that the metering
circuit is set for the higher current range. It also initialises
the LCD module, and then displays an initial greeting message on it to show that the meter is ‘active’.
After pausing a few seconds it then displays a second
message, advising the user to first set the test voltage (via
S1) and then press the Test button (S2) to start testing.
As soon as it senses (via RA4) that the Test button has
been pressed, it first checks the test voltage you have selected using S1. (It does this by checking the logic levels
on RA0 and RA7.) Then it directs the PIC’s ADC module
to make a sequence of 10 measurements of the voltage
applied to the AN2 input (which is the voltage across the
100Ω leakage current shunt, amplified by IC2a).
After taking the 10 measurements, it then works out the
average of these measurements by calculating their sum
and then dividing by 10. This averaging is done to give
more steady readings, because the individual measurements tend to vary as a result of ‘ripple’ on the output of
the DC-DC converter.
This average of the 10 measurements is then checked to
see if it is a ‘full scale’ reading, and if so the firmware checks
to determine the meter’s current range setting.
If it isn’t set for the higher current range, the meter is
S3 on, a reassuring glow should appear
from the LCD display window – from
the LCD module’s back-lighting You
may also be able to see the Meter’s
initial greeting ‘screen’, as shown in
one of the display photos at right.
If not, adjust contrast trimpot VR2
with a tiny screwdriver until you get
a clearly visible display. (VR2 is adjusted through the small hole just to
the left of the LCD window.)
After a few seconds, the display
should change to the Meter’s measurement guide ‘screen’, where it reminds
you to first set the test voltage using S1
and then press button S2 to perform
the test.
As soon as you do press the test
button, the display should change
into the Meter’s test result ‘screen’,
where it displays the test voltage plus
the measured leakage current and
resistance. At this stage it will show
a leakage current of 0A and a resistance of 999MΩ because you haven’t
connected anything between the two
test terminals to draw any current.
Now try switching voltage selector
switch S1 to the other positions. When
you then press and hold down S2 you
should find that the test voltage setting
displayed on the top line of the LCD
screen changes to match.
siliconchip.com.au
switched to the higher current range and the firmware loops
back to take another sequence of 10 measurements, and
work out their average.
If the average reading was not a full-scale one, or if it is
already set for the higher current range, the firmware then
does another check to see if the reading is below 10% of full
scale. If this is so, it checks to see if the meter is switched
to the lower current range.
If not, the meter is switched to the lower current range
and the firmware loops back once again to take another
sequence of 10 measurements and work out their average.
By doing this automatic range changing, the firmware
finally achieves an average reading with the best resolution
it is able to provide.
This reading is then processed by the firmware and its
24-bit floating point maths routines to calculate both the
leakage current (in mA or A) and the equivalent leakage
resistance in megohms.
These calculated values are then displayed on the LCD
screen, along with the test voltage being used.
One further little job done by the firmware is to check the
values being displayed for current and leakage resistance,
and if there are any ‘leading zeroes’ they are changed into
blanks. This is another improvement over the firmware in
the first version.
If this occurs it will show that your
Digital Insulation Meter is working
correctly.
Setting the test voltage
If everything seems OK at this stage,
it’s time to do the final adjustment:
setting the test voltage levels. This
is easy enough to do because it simply involves monitoring the DC-DC
converter’s output voltage on a single
range with your DMM, while carefully
adjusting trimpot VR1 using a long and
narrow insulated screwdriver.
Here’s the procedure: first turn off
the power to the Digital Insulation
Meter using S3. Then swing up the lid
and main board assembly to allow you
to access the DC-DC converter board.
Next connect the DMM’s positive
lead to the “+HV out” terminal pin
at the rear of the converter board just
above D3 and connect the DMM’s
negative lead to one of the two ‘earth’
terminal pins of the same board. The
TPG pin just above TP3 may be easier
to access, but you can use the centre
(GND) pin on the right-hand end of
the board if you prefer.
Now turn the DMM on, and select
the 500V DC range (or higher). Then
turn on the meter using S3, switch S1
to its ‘250V’ position and then care-
fully press and hold down S2 and
the DMM reading should be around
250V. Then adjust trimpot VR1 to give
a reading of 225V.
By doing this, the resultant test voltage across a 1MΩ load should be very
close to the setting.
Alternatively, if you envisage testing
equipment with internal MOVs, etc
and possibly portable RCDs, do the
voltage adjustment on the 250V range.
In this case, adjust trimpot VR1 to give
a reading of 265V. This will result in
a test voltage across a 100kΩ load of
close to 250V.
(Those pedantic readers who have
very accurate DMMs may prefer to
make the adjustment to 262V but the
resulting test voltage will still depend
on the overall resistor tolerances.)
Either way, you only have to adjust
VR1 on one range as the other ranges
will be pretty close to their nominal
values.
Once you are satisfied with the
voltage adjustment, you can turn off
the power via S3, remove your DMM
measuring leads and refit the lid assembly into the box.
You can then fit the screws which
hold the lid and box together and your
Digital Insulation Meter is now ready
for use.
SC
June 2010 89
|